District 210 Awards $24.4 Million Contract for Major HVAC Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | December 18, 2025

Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.

Mechanical Upgrades Key Points:

  • Total Contract Value: $24,419,400 awarded to BEAR Construction Company.

  • Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.

  • Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.

  • Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.

The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.

District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.

“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”

One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.

Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.

Leave a Comment





Latest News Stories

Will County Board Graphic.04

County Approves Engineering for Peotone Road and Safety Upgrades

Will County Board Meeting | December 18, 2025 Article Summary: The County Board approved a Phase I engineering contract for improvements to Wilmington-Peotone Road and authorized an agreement for license...
U.S. Coast Guard broke records across the board in 2025

U.S. Coast Guard broke records across the board in 2025

By Bethany BlankleyThe Center Square (The Center Square ) – In 2025, the U.S. Coast Guard broke records across the board as the Trump administration poured an historic amount of...
Don’t count on lower electricity prices in 2026

Don’t count on lower electricity prices in 2026

By Lauren JessopThe Center Square For 67 million people relying on electricity from the regional power grid, PJM, cheaper utility bills in 2026 are little more than a pipe dream....
Screenshot 2025-12-20 at 12.27.11 PM

Lincoln-Way Board Approves $731,000 Freshman Laptop Purchase

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The District 210 Board of Education authorized the purchase of 1,750 Lenovo laptops to equip the incoming...
Will County Board Graphic.01

Monee Solar Farm Projects Granted Extensions

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee...

WATCH: Report: Americans are still paying off credit debt from last Christmas

By Carleen JohnsonThe Center Square If your last-minute Christmas shopping requires a credit card, you are not alone. According to a new WalletHub report, many Americans are still paying off...
Congressional Conflicts: Curb on lawmakers’ stock trades draws fire for being weak

Congressional Conflicts: Curb on lawmakers’ stock trades draws fire for being weak

By Mark StricherzThe Center Square A limited ban on stock trading by Congress might get a vote next year after a 2012 law did not do enough to stem the...
Wyoming's year in review: Education savings, contentious spending

Wyoming’s year in review: Education savings, contentious spending

By Andrew RiceThe Center Square Wyoming lawmakers passed legislation to expand education savings accounts and property tax protections in 2025. However, the legislature remained divided on substantial spending increases to...
Sufyan Farhan

Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom

Article Summary: Sufyan Farhan, 27, was arrested on December 21 following an armed robbery at a Frankfort Circle K. Deputies located the suspect hiding in a nearby McDonald's restroom after...
U.S. House advances GOP-backed energy reliability bill

U.S. House advances GOP-backed energy reliability bill

By Elyse ApelThe Center Square Legislation looking to lower energy prices nationally successfully passed the U.S. House on a slightly bipartisan vote. H.R. 3628, titled the “State Planning for Reliability...
Illinois’ safe gun storage law goes into effect Jan. 1

Illinois’ safe gun storage law goes into effect Jan. 1

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Components of Illinois Safe Gun Storage Act go into effect Jan. 1. Supporters of Senate Bill 8,...
manhattan fire district graphic logo.1

Manhattan Fire Trustees Approve 2026 Budget and Tax Levy; Workers’ Comp Costs Jump 20%

Manhattan Fire Protection District Meeting | Nov. 17, 2025 Article Summary: The Manhattan Fire Protection District Board of Trustees adopted its budget and tax levy for the upcoming year while...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Village Board for December 16, 2025

Manhattan Village Board Meeting | December 16, 2025 The Manhattan Village Board on Tuesday, Dec. 16, 2025, conducted a brief regular session focused on infrastructure maintenance and holiday community events....