District 210 Awards $24.4 Million Contract for Major HVAC Upgrades
Lincoln-Way Community High School District 210 Meeting | December 18, 2025
Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.
Mechanical Upgrades Key Points:
-
Total Contract Value: $24,419,400 awarded to BEAR Construction Company.
-
Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.
-
Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.
-
Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.
The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.
The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.
District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.
“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”
One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.
Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.
Latest News Stories
Jackson Township Prepares for Property Viability Pole Relocation, Addresses Northpoint Traffic Control
Manhattan School District Explores Alternative Transportation Amid Lincoln-Way Bus Challenges
Manhattan Ranked 6th Safest City in Illinois; Police Chief Warns of Traffic Accidents
Manhattan Township Assessor Initiates $13,500 Software Upgrade Amid Office Transition
Manhattan and New Lenox Renew Boundary Agreement Through 2046
Manhattan Board Approves Route 52 Safety Study and Multi-Use Path Engineering
State of the College: Local Legislators Bolster Student Support Services
Meeting Summary and Briefs: Public Health & Safety Committee for February 5, 2026
State of the College: Dual Credit Program Enrollment Hits 6,000 Students
Meeting Summary and Briefs: Finance Committee for February 3, 2026
Fairmont Neighborhood Plan Update Prioritizes Infrastructure and Beautification Following Demographic Shift
Health & Safety Committee: Monee Church Kitchen Project Highlighted in County Health Impact Report