Construction Advances on New Manhattan Fire Station; Ambulance Repairs Scheduled

Spread the love

Manhattan Fire Protection District Meeting | Nov. 17, 2025

Article Summary: Fire Chief Steve Malone updated the board on the progress of the new fire station, reporting that the apparatus bay is erected and concrete work is underway. The district is also managing a rotation of ambulance repairs following recent traffic accidents.

Operations and Facilities Key Points:

  • Station Construction: The apparatus bay at the new station is up, concrete slabs are being poured, and electrical work is progressing.

  • Ambulance Rotation: Ambulance 81 was involved in a minor accident but remains operable; it will undergo repairs once a previously crashed ambulance returns to service in late December.

  • Peotone Coordination: The Fire Marshal is waiting for the Village of Peotone to pass updated fire codes, and the district has finalized a “Standard of Cover” document merging Manhattan and Peotone data.

The Manhattan Fire Protection District Board of Trustees on Monday, November 17, 2025, received updates on capital projects and fleet maintenance, including the status of the new fire station construction.

Chief Steve Malone reported that work on the new station is moving forward, with the apparatus bay structure now standing. Crews are currently pouring concrete slabs and advancing the electrical systems.

In fleet news, Chief Malone informed the board that Ambulance 81 was involved in a minor traffic accident. While the vehicle remains operable for the time being, it will eventually need to go out of service for repairs. The Battalion Chief’s report indicated that the district is waiting for another ambulance—which had crashed last year—to return to service by late December. Once that vehicle is back, Ambulance 81 will be taken offline for its repairs.

The Battalion Chiefs also noted that two new brush trucks are scheduled for delivery by the end of 2026.

The meeting also highlighted administrative coordination with the Village of Peotone. The Fire Marshal reported that the district is currently waiting for Peotone to pass updated fire codes. Additionally, Chief Malone noted that the new “Standard of Cover” document has been finalized, utilizing five years of data that merges information from both Peotone and Manhattan.

Leave a Comment





Latest News Stories

lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
District 114 Graphic

Manhattan School District 114 Approves $41.5 Million Budget for FY26

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a fiscal year 2026 budget with $41.5 million in expenditures, a figure significantly influenced by the final costs...
Peotone fire district graphic logo.1

Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings

Article Summary: The Manhattan Fire Protection District is moving forward with plans for a new Station 81 after holding a public hearing for an $8.75 million bond sale and approving...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...