Construction Advances on New Manhattan Fire Station; Ambulance Repairs Scheduled
Manhattan Fire Protection District Meeting | Nov. 17, 2025
Article Summary: Fire Chief Steve Malone updated the board on the progress of the new fire station, reporting that the apparatus bay is erected and concrete work is underway. The district is also managing a rotation of ambulance repairs following recent traffic accidents.
Operations and Facilities Key Points:
-
Station Construction: The apparatus bay at the new station is up, concrete slabs are being poured, and electrical work is progressing.
-
Ambulance Rotation: Ambulance 81 was involved in a minor accident but remains operable; it will undergo repairs once a previously crashed ambulance returns to service in late December.
-
Peotone Coordination: The Fire Marshal is waiting for the Village of Peotone to pass updated fire codes, and the district has finalized a “Standard of Cover” document merging Manhattan and Peotone data.
The Manhattan Fire Protection District Board of Trustees on Monday, November 17, 2025, received updates on capital projects and fleet maintenance, including the status of the new fire station construction.
Chief Steve Malone reported that work on the new station is moving forward, with the apparatus bay structure now standing. Crews are currently pouring concrete slabs and advancing the electrical systems.
In fleet news, Chief Malone informed the board that Ambulance 81 was involved in a minor traffic accident. While the vehicle remains operable for the time being, it will eventually need to go out of service for repairs. The Battalion Chief’s report indicated that the district is waiting for another ambulance—which had crashed last year—to return to service by late December. Once that vehicle is back, Ambulance 81 will be taken offline for its repairs.
The Battalion Chiefs also noted that two new brush trucks are scheduled for delivery by the end of 2026.
The meeting also highlighted administrative coordination with the Village of Peotone. The Fire Marshal reported that the district is currently waiting for Peotone to pass updated fire codes. Additionally, Chief Malone noted that the new “Standard of Cover” document has been finalized, utilizing five years of data that merges information from both Peotone and Manhattan.
Latest News Stories
WATCH: IL Republican pushes for TX quorum rules that Pritzker hails as ‘hero’ move
Manhattan Police Report
Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash
Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond
Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns
IT Consultant Urges Green Garden Township to Adopt Modern Cybersecurity Measures
Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property
Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Sheepdog Firearms Gets Green Light for Special Use Permit in Monee
New Lenox Prepares for Grand Opening of Wintrust Crossroads Sports Complex
New Lenox D122 Board Approves Tentative Budget, Sets September Public Hearing
New Lenox Township Food Pantry Reports Record Demand in May