Construction Advances on New Manhattan Fire Station; Ambulance Repairs Scheduled

Spread the love

Manhattan Fire Protection District Meeting | Nov. 17, 2025

Article Summary: Fire Chief Steve Malone updated the board on the progress of the new fire station, reporting that the apparatus bay is erected and concrete work is underway. The district is also managing a rotation of ambulance repairs following recent traffic accidents.

Operations and Facilities Key Points:

  • Station Construction: The apparatus bay at the new station is up, concrete slabs are being poured, and electrical work is progressing.

  • Ambulance Rotation: Ambulance 81 was involved in a minor accident but remains operable; it will undergo repairs once a previously crashed ambulance returns to service in late December.

  • Peotone Coordination: The Fire Marshal is waiting for the Village of Peotone to pass updated fire codes, and the district has finalized a “Standard of Cover” document merging Manhattan and Peotone data.

The Manhattan Fire Protection District Board of Trustees on Monday, November 17, 2025, received updates on capital projects and fleet maintenance, including the status of the new fire station construction.

Chief Steve Malone reported that work on the new station is moving forward, with the apparatus bay structure now standing. Crews are currently pouring concrete slabs and advancing the electrical systems.

In fleet news, Chief Malone informed the board that Ambulance 81 was involved in a minor traffic accident. While the vehicle remains operable for the time being, it will eventually need to go out of service for repairs. The Battalion Chief’s report indicated that the district is waiting for another ambulance—which had crashed last year—to return to service by late December. Once that vehicle is back, Ambulance 81 will be taken offline for its repairs.

The Battalion Chiefs also noted that two new brush trucks are scheduled for delivery by the end of 2026.

The meeting also highlighted administrative coordination with the Village of Peotone. The Fire Marshal reported that the district is currently waiting for Peotone to pass updated fire codes. Additionally, Chief Malone noted that the new “Standard of Cover” document has been finalized, utilizing five years of data that merges information from both Peotone and Manhattan.

Leave a Comment





Latest News Stories

Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
MH 114 June 2

Manhattan School Board Approves Staff Changes, Healthcare Extension in Special Session

Manhattan School District 114's Board of Education approved several personnel changes and a healthcare extension during a special meeting Monday evening, conducting most of its business in closed session. The...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting Briefs

School District 114 June 2 Meeting Briefs

Staff Departures: Manhattan School District 114 accepted the resignations of Emily Corcoran and Caroline Pesa-Miller, both effective at the end of the 2025 school year. The board approved both resignations...
Meeting Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
MH VB 5--22

Manhattan Board Changes Meeting Time, Limits Public Comment

Village moves to 5:30 p.m. start time and reduces speaking period from five to three minutes The Village of Manhattan Board of Trustees approved two ordinance changes Tuesday that will...
MH VB 5--22

Manhattan Challenges Neighboring Villages to Pop Tab Competition

Community fundraising effort for Ronald McDonald House expands to include multiple villages The Village of Manhattan has officially challenged neighboring communities to a summer-long pop tab collection competition benefiting the...
Meeting Briefs

Manhatttan Village Board Meeting Briefs

MUNICIPAL UPDATES Memorial Day Services Planned: The I Honor Banner Ceremony will take place Sunday at 10 a.m. at the Manhattan Township Building, 230 S. Wabash Street. The ceremony dedicates...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
MFPD-Logo-Fire District

Fire Station Construction Bids Due June 3, Storm Generates 40 Emergency Calls

The Manhattan Fire Protection District has received strong interest from contractors for its new fire station project, with construction bids due back June 3 and groundbreaking still targeted for July....
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
MFPD-Logo-Fire District

Fire District Maintains Strong Call Volume, Equipment Readiness

The Manhattan Fire Protection District is maintaining steady emergency response capabilities while addressing routine equipment maintenance needs across its two-station operation. Deputy Chief Dave Piper's April operational report showed continued...