Facilities Director Bill Fern provided updates on major renovation projects, including the completion of the Court Annex and the impending opening of the Veterans Assistance Commission (VAC) building. The committee also addressed critical repairs, including a lingering elevator outage at the Health Department.

Facilities Update Key Points:

  • Court Annex: Renovations at 57 N. Ottawa are complete, and staff has moved into the new office spaces.

  • VAC Facility: The new Veterans Assistance Commission building at 1300 Copperfield is expected to reach substantial completion by mid-January 2026.

  • In-House Savings: County staff completed water main repairs at the River Valley Justice Center in-house, saving the county approximately $15,000.

  • Elevator Outage: A proprietary elevator at the Health Department has been out of service since November, with inspectors scheduled to visit January 7.

The Will County Board Capital Improvements and IT Committee on Tuesday, January 6, 2026, received a status report on county infrastructure from Facilities Director Bill Fern.

Fern reported that the renovations at the Court Annex and State’s Attorney’s office at 57 N. Ottawa are complete. “They’ve moved in. It’s a beautiful new space,” Fern told the committee, noting that previously boarded-up windows were opened to provide natural light for the new offices.

Progress continues at the new Veterans Assistance Commission (VAC) facility at 1300 Copperfield. Major renovations, including boilers, flooring, and the facade, are nearly finished. Fern stated that substantial completion is expected by mid-January, though a final move-in date is floating due to contractor material issues.

The committee also addressed a significant maintenance issue at the Will County Health Department, where an elevator has been out of service since November. Fern explained that the unit is a unique, proprietary hydraulic elevator that serves only one floor, complicating repairs.

“It’s a little concerning the Health Department [has] to help make accommodations for the people that were displaced,” Fern acknowledged.

Fern confirmed that a team of inspectors was scheduled to visit the site on the morning of January 7 to pinpoint why the car is not leveling properly. Committee Vice-Chair Dave Oxley (R-Lockport) requested immediate updates following the inspection to ensure the issue is resolved for the public.

Fern also highlighted the work of the county’s skilled tradesmen, noting that a water main leak at the River Valley Justice Center was repaired in-house overnight, saving the county an estimated $15,000 and avoiding operational disruptions.

Leave a Comment





Latest News Stories

Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
District 114 Graphic

Manhattan School District 114 Approves $41.5 Million Budget for FY26

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a fiscal year 2026 budget with $41.5 million in expenditures, a figure significantly influenced by the final costs...
Peotone fire district graphic logo.1

Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings

Article Summary: The Manhattan Fire Protection District is moving forward with plans for a new Station 81 after holding a public hearing for an $8.75 million bond sale and approving...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...