Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual approach that includes both vertical and horizontal growth. Consultants revealed a complex engineering solution involving a diversion berm and pulley system to manage leachate collection as new cells are constructed over existing infrastructure.

Landfill Expansion Key Points:

  • Expansion Strategy: The county is pursuing both vertical (upward) and horizontal (outward) expansion simultaneously.

  • Engineering Challenge: A significant hurdle involves maintaining leachate collection from the existing landfill while building new cells on top of it. Consultants designed a 94-foot-wide phase delineation berm and a “pipe within a pipe” pulley system to address this.

  • Soil Pile Obstacle: A large soil stockpile remains on site without a current plan for relocation, necessitating the dual-track design approach. Discussions with neighboring Local 150 regarding land acquisition have stalled but may be restarted.

The Will County Board Landfill Committee received a comprehensive update on Tuesday, January 13, 2026, regarding the ongoing design and planning for the Prairie View Landfill expansion.

Marty Fallon of Geologic Associates, the county’s landfill consultant, presented the latest engineering schematics, highlighting the project’s complexity. The expansion strategy involves a “piggyback” design where new landfill cells will be constructed partially on top of the existing waste mound.

“One of the challenges that we’ve had here with this horizontal expansion… we’re going to cover up a portion of the existing landfill,” Fallon explained. This creates a conflict with the existing leachate collection sumps.

To solve this, consultants have designed a massive 94-foot-wide “phase delineation berm” to separate the old and new sections. Within this berm, they plan to install a specialized diversion system featuring a 24-inch pipe housing a smaller 12-inch pipe with a pulley mechanism. This “straw within a straw” design will allow pumps to be retrieved for maintenance even after they are buried under tons of new waste.

Fallon also addressed a critical logistical issue: a large soil stockpile currently occupying space needed for the horizontal expansion. “Currently we don’t have a plan to move that,” Fallon stated, noting that off-site relocation is required.

This issue sparked discussion about reviving negotiations with Local 150, which owns adjacent property. Chuck Helston, outside counsel for the county, confirmed that previous confidential discussions had stalled but expressed willingness to re-engage at the committee’s direction.

Committee Chair David Oxley suggested a creative solution for the union: “Perhaps they could use that as training for their employees and their apprentices to move that dirt to that pile.” Helston agreed to raise the idea again.

The expansion is not expected to disrupt operations at the adjacent Renewable Natural Gas (RNG) plant. “It won’t be any disruption to the [RNG plant] none,” Fallon assured the committee.

Leave a Comment





Latest News Stories

diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
District 114 Bus

Parents Voice Alarms Over Bus Safety, Lateness in Manhattan School District

Article Summary: Parents raised serious transportation safety and reliability concerns at the Manhattan School District 114 board meeting, including a harrowing account of a kindergartener being dropped off at the...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for September 16, 2025

The Manhattan Village Board took steps to prepare for future growth at its Tuesday meeting, awarding a contract of over half a million dollars to extend water and sewer infrastructure...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
Screenshot 2025-09-27 at 8.39.48 AM

Manhattan Police Department Promotes Garrison to Commander, Diaz to Sergeant

Article Summary: The Manhattan Police Department solidified its command structure with the promotions of William Garrison to the rank of Commander and Bryan Diaz to Sergeant, who were both officially...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for August 18, 2025

Manhattan Fire Protection District | August 18, 2025 Meeting The Manhattan Fire Protection District Board of Trustees focused on the future of its facilities and public safety at its meeting...
Screenshot 2025-09-27 at 8.36.16 AM

Village of Manhattan Honors St. Joseph’s Catholic School on its 100th Anniversary

Article Summary: The Village of Manhattan celebrated a major community milestone at its Tuesday board meeting, officially honoring St. Joseph's Catholic School for its 100th anniversary with a formal proclamation...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Screenshot 2025-09-27 at 8.36.16 AM

Manhattan Awards $547K Contract for US 52 Infrastructure Extension to Spur Growth

Article Summary: The Village of Manhattan has awarded a $547,449 contract to Speece Construction for a significant sewer and water main extension project along the US 52, Smith Road, and...
manhattan fire district graphic logo.3

Fire District to Address Safety at High-Accident Intersections with County DOT

Manhattan Fire Protection District | August 18, 2025 Meeting Article Summary: The Manhattan Fire Protection District will meet with the Will County Department of Transportation to provide data and seek...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for August 2025

Manhattan Township Meeting | August 2025 The Manhattan Township Board took steps to address the growing interest in renewable energy at its meeting on Tuesday, August 12, 2025, by scheduling...
Screenshot 2025-09-27 at 8.16.09 AM

Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate...