Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual approach that includes both vertical and horizontal growth. Consultants revealed a complex engineering solution involving a diversion berm and pulley system to manage leachate collection as new cells are constructed over existing infrastructure.

Landfill Expansion Key Points:

  • Expansion Strategy: The county is pursuing both vertical (upward) and horizontal (outward) expansion simultaneously.

  • Engineering Challenge: A significant hurdle involves maintaining leachate collection from the existing landfill while building new cells on top of it. Consultants designed a 94-foot-wide phase delineation berm and a “pipe within a pipe” pulley system to address this.

  • Soil Pile Obstacle: A large soil stockpile remains on site without a current plan for relocation, necessitating the dual-track design approach. Discussions with neighboring Local 150 regarding land acquisition have stalled but may be restarted.

The Will County Board Landfill Committee received a comprehensive update on Tuesday, January 13, 2026, regarding the ongoing design and planning for the Prairie View Landfill expansion.

Marty Fallon of Geologic Associates, the county’s landfill consultant, presented the latest engineering schematics, highlighting the project’s complexity. The expansion strategy involves a “piggyback” design where new landfill cells will be constructed partially on top of the existing waste mound.

“One of the challenges that we’ve had here with this horizontal expansion… we’re going to cover up a portion of the existing landfill,” Fallon explained. This creates a conflict with the existing leachate collection sumps.

To solve this, consultants have designed a massive 94-foot-wide “phase delineation berm” to separate the old and new sections. Within this berm, they plan to install a specialized diversion system featuring a 24-inch pipe housing a smaller 12-inch pipe with a pulley mechanism. This “straw within a straw” design will allow pumps to be retrieved for maintenance even after they are buried under tons of new waste.

Fallon also addressed a critical logistical issue: a large soil stockpile currently occupying space needed for the horizontal expansion. “Currently we don’t have a plan to move that,” Fallon stated, noting that off-site relocation is required.

This issue sparked discussion about reviving negotiations with Local 150, which owns adjacent property. Chuck Helston, outside counsel for the county, confirmed that previous confidential discussions had stalled but expressed willingness to re-engage at the committee’s direction.

Committee Chair David Oxley suggested a creative solution for the union: “Perhaps they could use that as training for their employees and their apprentices to move that dirt to that pile.” Helston agreed to raise the idea again.

The expansion is not expected to disrupt operations at the adjacent Renewable Natural Gas (RNG) plant. “It won’t be any disruption to the [RNG plant] none,” Fallon assured the committee.

Leave a Comment





Latest News Stories

manhattan fire district graphic logo.1

Construction Progresses on New Manhattan Fire Station, August Completion Anticipated

Manhattan Fire Protection District Meeting | February 17, 2026 Article Summary: The Manhattan Fire Protection District's new fire station is advancing rapidly through its construction phases, with concrete work finished...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...
Monee Fire

Barn Fire on Whispering Hills Lane Claims Livestock, Draws Extensive Mutual Aid Response

Article Summary: A massive late-night structure fire completely destroyed a 60-by-60-foot wood frame barn on Whispering Hills Lane, resulting in the loss of 15 animals but no human injuries. Firefighters from...
Will County Board Graphic.01

Will County Public Works Committee Shelves License Plate Reader Agreement Amid Bipartisan Privacy Concerns

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee abruptly removed an agreement with the Illinois State Police...
Will County P&Z Logo Planning Zoning.2

Will County Planning and Zoning Commission Overrides Staff to Approve New Lenox Accessory Building Variance

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission voted to override a staff recommendation of denial, approving a...
sheriff dog

Will County Sheriff’s Office Welcomes Remi, First Electronic Scent Detection Dog

Article Summary: The Will County Sheriff’s Office announced the addition of Remi, a Labrador serving as the department's first Electronic Scent Detection dog. The newly trained K9 will assist investigators...
Will County Public Works Committee

Will County Transportation Department Announces Open House for Manhattan-Monee Road Expansion

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Division of Transportation is inviting residents to a public open house on March 19...
Will County Board Graphic.04

Will County Community Mental Health Board Faces $5 Million Shortfall in 2026 Grant Requests

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Community Mental Health Board has received over $9 million in funding requests for its 2026 grant cycle,...
Will County Board Graphic.01

Meeting Summary and Briefs: Public Health & Safety Committee for March 5, 2026

Public Health & Safety Committee Meeting | March 5, 2026 The Will County Public Health and Safety Committee met on Thursday to address critical infrastructure and wellness updates across the...
Sheriff Scam Alert Graphic

Will County Officials Warn of Zoom Court Scam Targeting Defendants for Fraudulent Dismissal Fees

Article Summary: Will County officials have issued an alert regarding a fraudulent scheme where scammers infiltrate courtroom Zoom sessions to extort money from defendants. The perpetrators use private chat features...
Will County Board Land Use Committee Graphic.3

Will Land Use Committee Evaluates Multi-Million Dollar Buyout for Flooded Harris Drive Homes

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee is exploring a multi-million-dollar buyout program for several homes...