Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Illinois’ ‘F’ grade leaves taxpayers on the hook for billions, watchdog says

Illinois’ ‘F’ grade leaves taxpayers on the hook for billions, watchdog says

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Budget gimmicks, pension debt and late financial reports are leaving Illinois taxpayers in the dark, according...
Illinois quick hits: Chicago Jewish Alliance on peace developments; Blue Ribbon Schools announced

Illinois quick hits: Chicago Jewish Alliance on peace developments; Blue Ribbon Schools announced

By Jim Talamonti | The Center SquareThe Center Square Chicago Jewish Alliance on peace developments The Chicago Jewish Alliance has offered a response to the release of 20 hostages held...
WATCH: Trump’s emergency Guard appeal denied; Fiscal Fallout reviews state salaries

WATCH: Trump’s emergency Guard appeal denied; Fiscal Fallout reviews state salaries

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop gets to the...
Reforms prompt big money appeals in IL biometrics cases

Reforms prompt big money appeals in IL biometrics cases

By Jonathan Bilyk | Legal NewslineThe Center Square Even as reforms seem to have edged down the number of biometric privacy lawsuits targeted at businesses in Illinois, appeals courts are...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for October 9, 2025

The Will County Board’s Executive Committee held a contentious meeting on Thursday, October 9, 2025, dominated by debates over public access and a controversial resolution concerning immigrant rights. A proposal...
Screenshot 2025-10-10 at 11.36.53 AM

Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County's new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while...
Screenshot 2025-10-10 at 11.20.34 AM

Will County Considers First Update to Wastewater Ordinance Since 2016

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is preparing to update its ordinance governing private wastewater systems, with proposed changes including the...
Screenshot 2025-10-10 at 12.12.11 PM

IDOT Plans to Invest Over $1.3 Billion in Will County Roads Through 2031

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Illinois Department of Transportation (IDOT) has allocated over $1.3 billion for road and bridge projects in...
Screenshot 2025-10-10 at 11.39.54 AM

Committee Advances 50% Increase in Mental Health Levy on 4-3 Vote

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a proposed $12 million levy for the Community Mental Health Board,...
Screenshot 2025-10-10 at 11.19.48 AM

Will County Poised to Launch Major Mental Health Initiative Based on Joliet Program’s Success

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Board Public Health & Safety Committee on Thursday considered establishing "Will County CARES," a...
Screenshot 2025-10-10 at 12.05.35 PM

Looming State Energy Bill Threatens to Further Limit County Control Over Solar and Wind Projects

Will County Legislative Committee Meeting October 7, 2025 Article Summary: A state energy bill likely to be considered during the fall veto session or next spring could further strip Will...
Screenshot 2025-10-10 at 11.52.31 AM

Controversial Immigrant Rights Resolution Postponed by Will County Board After Heated Debate

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Executive Committee voted to indefinitely postpone a contentious resolution titled "Declaring Will County's Commitment to Ensure Communities...
Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Will County Finance Committee Meeting October 7, 2025 Article Summary: Will County's Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the...
Screenshot 2025-10-10 at 11.36.47 AM

Will County to Draft First-Ever Policy on Artificial Intelligence Use

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: The Will County Board's Capital Improvements & IT Committee has initiated the process of drafting a comprehensive...
Screenshot 2025-10-10 at 11.20.18 AM

Will County Sees 50% Drop in Opioid Deaths, But Alarming Rise in Suicides

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is experiencing a dramatic 50% reduction in opioid overdose deaths compared to last year, a...