Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
District 114 Bus

Parents Voice Alarms Over Bus Safety, Lateness in Manhattan School District

Article Summary: Parents raised serious transportation safety and reliability concerns at the Manhattan School District 114 board meeting, including a harrowing account of a kindergartener being dropped off at the...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for September 16, 2025

The Manhattan Village Board took steps to prepare for future growth at its Tuesday meeting, awarding a contract of over half a million dollars to extend water and sewer infrastructure...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
Screenshot 2025-09-27 at 8.39.48 AM

Manhattan Police Department Promotes Garrison to Commander, Diaz to Sergeant

Article Summary: The Manhattan Police Department solidified its command structure with the promotions of William Garrison to the rank of Commander and Bryan Diaz to Sergeant, who were both officially...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for August 18, 2025

Manhattan Fire Protection District | August 18, 2025 Meeting The Manhattan Fire Protection District Board of Trustees focused on the future of its facilities and public safety at its meeting...
Screenshot 2025-09-27 at 8.36.16 AM

Village of Manhattan Honors St. Joseph’s Catholic School on its 100th Anniversary

Article Summary: The Village of Manhattan celebrated a major community milestone at its Tuesday board meeting, officially honoring St. Joseph's Catholic School for its 100th anniversary with a formal proclamation...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Screenshot 2025-09-27 at 8.36.16 AM

Manhattan Awards $547K Contract for US 52 Infrastructure Extension to Spur Growth

Article Summary: The Village of Manhattan has awarded a $547,449 contract to Speece Construction for a significant sewer and water main extension project along the US 52, Smith Road, and...
manhattan fire district graphic logo.3

Fire District to Address Safety at High-Accident Intersections with County DOT

Manhattan Fire Protection District | August 18, 2025 Meeting Article Summary: The Manhattan Fire Protection District will meet with the Will County Department of Transportation to provide data and seek...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for August 2025

Manhattan Township Meeting | August 2025 The Manhattan Township Board took steps to address the growing interest in renewable energy at its meeting on Tuesday, August 12, 2025, by scheduling...
Screenshot 2025-09-27 at 8.16.09 AM

Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate...