Meeting Summary and Briefs: Will County Landfill Committee for Jan. 13, 2026
Will County Landfill Committee Meeting | Jan. 13, 2026
The Will County Board Landfill Committee met on Tuesday, January 13, 2026, to address operational improvements at the Prairie View Landfill and its associated Renewable Natural Gas (RNG) plant. The meeting focused on future expansion plans, litter control, and significant capital equipment investments aimed at increasing revenue reliability.
RNG Plant Equipment Rental Review:
The committee discussed the ongoing rental costs for a telehandler and manlift at the RNG plant, which currently total nearly $12,000 per month. Committee members directed staff to investigate the feasibility of purchasing the equipment outright or converting the rental agreement to a lease-to-own model to save money. Staff was also instructed to stop renting the equipment through a third-party contractor to avoid markups and instead rent directly from the supplier.
Vertical vs. Horizontal Expansion:
Consultants confirmed that the county is pursuing both vertical and horizontal expansion permits for the landfill simultaneously. While vertical expansion is straightforward, the horizontal plan requires complex engineering to divert leachate pipes around existing waste cells.
Confidential Negotiations:
The committee briefly discussed stalled negotiations with Local 150 regarding land acquisition needed for the landfill expansion. Outside counsel Chuck Helston agreed to re-initiate contact with the union’s general counsel, potentially offering a land-for-dirt-removal deal that could serve as a training opportunity for union apprentices.
Tarping Enforcement:
Board Member Herbert Brooks Jr. raised questions about enforcing tarping regulations for trucks leaving the landfill. Staff clarified that while incoming trucks are required by state law to be tarped, the county’s host agreement also requires trucks to be clean before leaving. Staff committed to monitoring this more closely.
Return on Investment (ROI):
Regarding the proposed fourth compressor for the RNG plant, staff presented data estimating a 3 to 4.9-year return on investment. The additional unit is projected to stabilize production, allowing the plant to consistently hit higher revenue targets by avoiding downtime associated with the current three-compressor setup.
Latest News Stories
Will County Public Works Committee Juliy 1 Meeting Briefs
Manhattan Village Board Briefs
New Lenox Library Board Seats New Trustees, Reorganizes After Election
New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects
New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community
Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs
D122 to Spend $24,950 on Professional Enrollment Forecast
Manhattan Police Report
JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement
Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position
JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate
District 210 Approves Administrative Restructuring, Staff Salary Increases