Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.
Facilities Key Points:
-
Repair Cost: The final repair bill is estimated between $18,000 and $20,000.
-
Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.
-
In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.
-
Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.
JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.
During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.
“I think it was about $18,000 to $20,000,” Fern said.
Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.
“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”
Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.
In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.
“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.
By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.
Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.
Latest News Stories
Pro-life group criticizes judge for blocking defunding of Planned Parenthood again
Social Security updates for young and old pass U.S. House
Michigan farms supply Christmas trees nationwide, including to the White House
Chicago business activity down, unemployment rate up
WATCH: Pritzker encourages protests; Vaccine law signed; Chicago priorities criticized
Illinois quick hits: Trump signs Duckworth’s BABES Act; REAL ID portals promoted
With holiday season underway, temporary workers notified they don’t have to join a union
Lincoln-Way Board Approves Tutoring Service for Hospitalized Students
Meeting Summary and Briefs: Manhattan Fire Protection District for October 2025
Facing appeals loss, activists withdraw suit that had frozen ICE
Abbott asks Treasury Department to suspend Islam group’s tax-exempt status
Controversial Vietnamese film being considered for Oscars