Will County Public Works Debates Future Bridge Needs as 159th Street Closure Looms

Spread the love

Public Works & Transportation Committee Meeting | February 3, 2026

Article Summary: A discussion regarding the future deck repair of the 159th Street bridge in Lockport sparked a debate about the lack of alternative river crossings. Officials expressed concern over potential traffic gridlock when the bridge eventually closes for repairs, citing stalled plans for a new corridor.

159th Street Bridge Key Points:

  • Upcoming Closure: IDOT is planning a deck repair for the bridge over the Des Plaines River on 159th Street, tentatively scheduled around 2028.

  • Traffic Concerns: Board members fear severe congestion, as 159th Street is a primary artery.

  • Stalled Alternative: The Catton Farm/Bruce Road corridor project, which included a new bridge, remains stalled due to a lack of municipal agreement and funding.

The Public Works and Transportation Committee engaged in a candid discussion on Tuesday, February 3, 2026, regarding the fragility of the county’s east-west infrastructure, specifically concerning the 159th Street bridge in Lockport.

Committee Member Steve Balich (District 4) raised the issue, noting that the bridge is slated for a full closure for repairs in the coming years. He urged the committee to revisit plans for an alternative crossing to prevent traffic chaos.

“If 159th Street becomes a problem, there’s no way to get over the river unless you go down to Joliet or take 355,” Balich said. “We need another way to get over that river… because it’s going to be stopped. So the traffic’s going to be going crazy.”

Director of Transportation Jeff Ronaldson confirmed that the Illinois Department of Transportation (IDOT) is designing a deck repair for the bridge, which may occur around 2028. However, Ronaldson explained that the long-proposed alternative—the Catton Farm/Bruce Road corridor—is currently shelved.

Ronaldson detailed that federal requirements mandate the bridge be part of a larger corridor project, not a standalone structure. The project stalled because the municipalities along the route could not reach an agreement on funding the necessary road expansions leading up to the bridge.

“We can’t just lop it off at 53 and 171,” Ronaldson explained regarding the federal requirements. “You have to look at the whole corridor… and an agreement was not able to be made to make that happen.”

Member Dave Oxley (District 5) asked how the county could restart the process, noting the necessity of the project for his district. Ronaldson reiterated that the local agencies involved would need to come together to agree on funding and responsibilities, but admitted it is unclear who would take the lead.

Leave a Comment





Latest News Stories

Will County Finance Logo

Consultant Updates Finance Committee on Homer Glen Police Cost Study

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: A consultant hired to evaluate the financial implications of the Village of Homer Glen launching its own...
Lincoln Way West Track

Lincoln-Way West Girls Display Middle-Distance Strength at Central Invitational

The Lincoln-Way West girls’ track and field team battled through a deep and competitive field on Saturday, April 11, at the Lincoln-Way Central Girls Invitational. Competing against some of the...
Lincoln Way West Track

Lincoln-Way West Secures Eight Individual Victories, Takes Third in Varsity A at Best 4 Invitational

The Lincoln-Way West boys' track and field team showcased its elite top-end talent on Saturday, April 11, bringing home eight individual flight championships at the highly competitive Best 4 Invitational...
Lincoln Way West Warriors Softball

Oswego Outlasts Lincoln-Way West 5-3 in Nine-Inning Thriller

The Oswego varsity softball team relied on timely late-game heroics and a clutch relief pitching performance from Jaelynn Anthony to secure a hard-fought 5-3 victory over host Lincoln-Way West in...
Screenshot 2026-04-08 at 3.23.31 PM

Manhattan Renews Will County LPR Camera Agreement as Police Chief Highlights Crime-Solving Successes

Village of Manhattan Board of Trustees Meeting | April 7, 2026 Article Summary: The Village Board approved the renewal of an intergovernmental agreement to maintain two license plate reading cameras...
Screenshot 2026-04-10 at 1.52.27 PM

Manhattan 114 Board Advances Facility Upgrades and Reviews Transportation Bids

Manhattan School District 114 Board of Education Meeting | April 8, 2026 Article Summary: The Manhattan School District 114 Board of Education approved an independent contractor agreement for exterior upgrades...
Untitled design - 1

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...
Will County Finance Logo

Will County Finalizes 2025 Tax Levy at $159.5 Million, Limiting Rate Drops

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: The Will County Finance Committee reviewed the final 2025 tax levy extension numbers, which came in slightly...
Will County Board Graphic.02

Will County to Take Jurisdiction of Countyline Road Following $1.8 Million Agreement with Kankakee County

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County will absorb a 4.27-mile stretch of Countyline Road into its highway system, aided by...