Article Summary: The committee authorized an emergency expenditure of $155,000 to replace a failed walk-in freezer system at the Adult Detention Facility (ADF). The Sheriff’s Office reported that the 18-year-old system had completely failed, forcing the facility to rent freezer trucks at a high daily cost.

ADF Freezer Key Points:

  • Emergency Situation: The deep freeze system at the ADF failed completely, necessitating the use of rental freezer trucks costing $500 per day plus fuel.

  • Cost: The replacement contract with AMS Industries is valued at $149,450.

  • Funding: The funds will be drawn from the County Board’s contingency fund, as the Sheriff’s maintenance budget cannot cover the cost.

  • System Upgrade: The new system will feature separate compressors for better redundancy and ease of maintenance.

A critical failure of the walk-in freezer at the Will County Adult Detention Facility prompted swift action from the Finance Committee on Tuesday, February 3, 2026. The committee unanimously approved a $155,000 transfer from the county’s contingency fund to replace the facility’s refrigeration system.

Keith Breausche and Joseph Novak from the Sheriff’s Office maintenance division explained the urgency of the situation. “We lost the deep freeze at the ADF and right now we’re paying for two semi-trailer freezer trucks out there,” Novak said. He estimated the rental costs at $500 per day, not including fuel.

The existing system, which is 18 years old, suffered a catastrophic failure after multiple compressor replacements in recent years. “Now there’s just so much stuff built up in the line and the evaporator itself that it just keeps going into the new compressors and they keep failing,” Novak explained.

Member Jackie Traynere (District 11) expressed concern over the lack of planning for such an old piece of equipment. “To me, an 18-year-old freezer, that’s an accident waiting to happen,” she said. “I feel like maybe we’re missing some things.”

Breausche responded that while they knew the system was aging, the sudden total failure was unexpected. He added that the department has a “very long” list of priorities and limited budget.

The new system will separate the deep freeze compressors from the main cooling rack, which currently holds three coolers and the freezer on one skid. This change is expected to make future maintenance easier and provide better reliability.

Because the Sheriff’s Office does not have its own contingency line item large enough to cover the $149,450 bid, the money will be transferred from the County Board’s contingency fund.

Leave a Comment





Latest News Stories

Manhattan Township

Manhattan Township Bridge Project Saved After County Commissioner Intervenes with Forest Preserve

A critical bridge replacement project in Manhattan Township, jeopardized by a stalemate with the Will County Forest Preserve District and the potential loss of $500,000 in funding, has been saved...
Manhattan Township

Soltage Solar Farm Clears Township Hurdle with Detailed Landscaping Plan

A proposed solar farm by Soltage Renewable Energy has cleared a key local hurdle after its representative presented a detailed landscaping and aesthetics plan that satisfied the Manhattan Township Board....
Manhattan Township

Solar Developer Commits Up to $800,000 for Smith Road Improvements

Summit Ridge Energy, a solar farm developer, has committed to providing up to $800,000 for the engineering and construction of improvements along Smith Road, Manhattan Township officials announced Tuesday. The...
Manhattan Township

Meeting Briefs: Manhattan Township for February 11, 2025

Baker Road Bridge Work Imminent: Highway Commissioner Jim Baltas reported that the Road District crew will soon begin trimming trees to prepare for the upcoming construction on the Baker Road Bridge....
Manhattan Township

Manhattan Township to Review Solar Farm Proposal at Special Meeting

Manhattan Township will host a special meeting Jan. 28 to review a proposed solar farm development at the corner of Cherry Hill and Manhattan roads. Soltage Renewable Energy Provider has...
Manhattan Township

Manhattan Township Briefs

Township Approves $81,000 Assessor Budget: Manhattan Township trustees unanimously approved the 2025-2026 assessor's office budget request of $81,000 during their Jan. 14 meeting. The budget includes increases for employee salaries...
Jackson Township

Jackson Township Property Values to Rise 13% in 2025 Assessment

Jackson Township property owners will see assessed values increase by 13.18% in the upcoming assessment cycle, Assessor LeGrett reported at the township's January 8 monthly meeting. The increase, which will...
Jackson Township

Jackson Township Advances Infrastructure Projects Despite Winter Conditions

Jackson Township continues progress on major infrastructure improvements while maintaining winter road operations, officials reported at the January 8 township meeting. Supervisor Matt Robbins updated the board on the ongoing...
Jackson Township

Jackson Township Meeting Briefs

Meeting Approvals: Jackson Township trustees unanimously approved December 2024 meeting minutes and the monthly financial statement during their January 8 meeting. The board also approved the assessor's 2025 budget as...
Police blue and red flashing light on the car in the street

Manhattan Police Reports

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On November 25, officers cited Parker, Kenneth R (53) of...
Blue flasher light of siren of police car

Manhattan Police Reports

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On November 17, officers cited Randle, Devante (24) of...