Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Will County Executive Committee Meeting | February 11, 2026
Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.
Lorenzo Road Bridge Key Points:
-
Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.
-
Location: 1.25 miles west of I-55 in County Board District 1.
-
Total Cost: The estimated total project cost is $28,717,523.80.
-
Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.
-
Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.
The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.
The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.
According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.
Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.
The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.
The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.
Latest News Stories
Taxpayer risk cited after Bears stadium bill stalls
Illinois Quick Hits: General Assembly approves CTE bill
Amended scooter, e-bike bill heads to governor
Property tax-free Bears deal fails to pass
Illinois Quick Hits: Loyola student’s alleged killer charged with new felony
$55.9 billion budget includes new taxes, ‘no property tax relief’
Illinois to require bell-to-bell student phone ban in public schools
Meeting Summary and Briefs: Manhattan School District 114 for May 13, 2026
Illinois Quick Hits: Housing, megaprojects take backseat to budget talks
Taxpayer watchdog calls for accountability after helicopter prom controversy
Proposed $250 bill could be a boon for drug cartels, experts warn
Iowa voters head to the polls for fierce races