Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Spread the love

Will County Executive Committee Meeting | February 11, 2026

Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.

Lorenzo Road Bridge Key Points:

  • Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.

  • Location: 1.25 miles west of I-55 in County Board District 1.

  • Total Cost: The estimated total project cost is $28,717,523.80.

  • Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.

  • Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.

The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.

The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.

According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.

Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.

The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.

The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.

Leave a Comment





Latest News Stories

Will County Finance Logo

Consultant Updates Finance Committee on Homer Glen Police Cost Study

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: A consultant hired to evaluate the financial implications of the Village of Homer Glen launching its own...
Lincoln Way West Track

Lincoln-Way West Girls Display Middle-Distance Strength at Central Invitational

The Lincoln-Way West girls’ track and field team battled through a deep and competitive field on Saturday, April 11, at the Lincoln-Way Central Girls Invitational. Competing against some of the...
Lincoln Way West Track

Lincoln-Way West Secures Eight Individual Victories, Takes Third in Varsity A at Best 4 Invitational

The Lincoln-Way West boys' track and field team showcased its elite top-end talent on Saturday, April 11, bringing home eight individual flight championships at the highly competitive Best 4 Invitational...
Lincoln Way West Warriors Softball

Oswego Outlasts Lincoln-Way West 5-3 in Nine-Inning Thriller

The Oswego varsity softball team relied on timely late-game heroics and a clutch relief pitching performance from Jaelynn Anthony to secure a hard-fought 5-3 victory over host Lincoln-Way West in...
Screenshot 2026-04-08 at 3.23.31 PM

Manhattan Renews Will County LPR Camera Agreement as Police Chief Highlights Crime-Solving Successes

Village of Manhattan Board of Trustees Meeting | April 7, 2026 Article Summary: The Village Board approved the renewal of an intergovernmental agreement to maintain two license plate reading cameras...
Screenshot 2026-04-10 at 1.52.27 PM

Manhattan 114 Board Advances Facility Upgrades and Reviews Transportation Bids

Manhattan School District 114 Board of Education Meeting | April 8, 2026 Article Summary: The Manhattan School District 114 Board of Education approved an independent contractor agreement for exterior upgrades...
Untitled design - 1

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...
Will County Finance Logo

Will County Finalizes 2025 Tax Levy at $159.5 Million, Limiting Rate Drops

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: The Will County Finance Committee reviewed the final 2025 tax levy extension numbers, which came in slightly...
Will County Board Graphic.02

Will County to Take Jurisdiction of Countyline Road Following $1.8 Million Agreement with Kankakee County

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County will absorb a 4.27-mile stretch of Countyline Road into its highway system, aided by...