Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Manhattan-Elwood Public Library District Board for October 2025

Manhattan-Elwood Public Library District Board Meeting | October 2025 The Manhattan-Elwood Public Library District Board met on Tuesday, October 27, 2025, to conduct a Tax Levy Hearing and its regular...

Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: A renewal of an agreement allowing license plate reading (LPR) cameras in Peotone passed the Public Works Committee,...
Screenshot 2025-12-04 at 11.30.16 AM

No Accidents Reported Since Route 52 Stop Sign Installation; Local Business Donates Cameras

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: Police Chief Jeff Gulli reported that safety measures at the intersection of Route 52 and North Street...
manhattan elwood library graphic.2

Library Board Authorizes Online Bill Pay and Formalizes Friends of the Library Agreement

Manhattan-Elwood Public Library District Board Meeting | October 2025 Article Summary: The Manhattan-Elwood Public Library District Board moved to modernize financial operations by approving online bill payment services and solidifying...
Screenshot 2025-12-05 at 12.00.30 PM

Joliet Unity Movement Criticizes Board’s Handling of Cannabis Tax Revenue

Will County Board Meeting | December 4, 2025 Article Summary: During public comment, the Joliet Unity Movement denounced a recent board vote that redirected cannabis tax revenue away from community...

Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch...
Screenshot 2025-12-04 at 11.30.01 AM

Manhattan Trustees Approve 2025 Property Tax Levy

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: The Manhattan Village Board approved a property tax levy of approximately $3.8 million for the upcoming fiscal...
Screenshot 2025-12-05 at 11.56.48 AM

Tensions Flare as Board Members Clash Over Budget Process and Protocol

Will County Board Meeting | December 4, 2025 Article Summary: A special meeting intended to fix a budget error turned contentious as board members traded accusations regarding transparency, meeting conduct,...
Screenshot 2025-12-05 at 11.57.25 AM

Will County Board Approves $2.7 Million Reserve Draw to Finalize 0% Tax Levy

Will County Board Meeting | December 4, 2025 Article Summary: The Will County Board unanimously voted to transfer approximately $2.78 million from cash reserves to balance the fiscal year 2026...
Untitled design - 1

Manhattan-Elwood Library District Board Approves 2026-2030 Strategic Plan and Tax Levy

Manhattan-Elwood Public Library District Board Meeting | October 2025 Article Summary: The Manhattan-Elwood Public Library District Board of Trustees secured the institution's financial and operational future on Tuesday by approving...
Screenshot 2025-12-04 at 11.29.34 AM

Manhattan Annexes Historic Round Barn Farm; Plans for Wedding Venue Move Forward

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: The Manhattan Village Board officially annexed the historic Round Barn Farm Park into the village limits, paving...

Jackson Township to Hear Proposal for Manure-to-Gas Energy Facility

Article Summary: A proposal for an anaerobic digester facility that would convert hog manure into natural gas was brought to the attention of the Jackson Township Board. The project manager...

Meeting Summary and Briefs: Manhattan School District 114 for November 12, 2025

Manhattan School District 114 Meeting | November 12, 2025 The Manhattan School District 114 Board of Education held a meeting marked by profound community grief, a parent's emotional plea for...
Meeting-Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for November 20, 2025

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 The Lincoln-Way Community High School District 210 Board of Education held a busy meeting on Thursday, November 20, 2025,...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for October 2025

Manhattan Park Board Meeting | October 9, 2025 The Manhattan Park Board on Thursday, October 9, 2025, unanimously rejected a proposal for a conceptual site plan after developers declined to...