Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Revenues from energy production at $14.6B for 2025

Revenues from energy production at $14.6B for 2025

By Alton WallaceThe Center Square Energy production on federal lands and waters and in U.S. tribal areas generated $14.61 billion in government revenues in the 2025 fiscal year, according to...
IL congressman’s retirement announcement sparks calls for election fixes

IL congressman’s retirement announcement sparks calls for election fixes

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Common Cause Illinois is urging lawmakers to close what it calls an “anti-democratic” loophole after Rep....
WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop shares highlights from...
Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

By Jim Talamonti | The Center SquareThe Center Square Man arrested for threating legislator Illinois State Police Division of Criminal Investigation special agents have arrested a Chicago man on charges...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...
Screenshot 2025-11-21 at 1.05.10 PM

Manhattan Officials Praise IDOT’s ‘Swift Action’ on Route 52, Discuss Further Safety Measures

Manhattan Village Board Meeting | November 18, 2025 Article Summary:Manhattan Mayor Mike Adrieansen thanked the Illinois Department of Transportation for its quick response in adding safety measures at the Route...
manhattan park district graphic.1

Manhattan Park Board Rejects Site Plan Proposal, Halts Planning Over Cost Dispute

Manhattan Park Board Meeting | October 9, 2025 Article Summary: The Manhattan Park Board unanimously rejected a proposal for an architectural concept site plan from Arete Design Studio, effectively pausing...
Will County Board Graphic.02

Board Denies Appeal for “Tiny Home” RV Living in Crete

Will County Board Meeting | November 2025 Article Summary: The Will County Board voted 19-2 to uphold a denial of a temporary use permit for a recreational vehicle (RV) being...
Jackson Township Graphic.1 NEW

Jackson Township Board Notified of Proposal for 800-Acre Data Center

Jackson Township Board Meeting | October 2025 Article Summary: During the monthly report, township officials announced the receipt of a public notice regarding a massive proposal to construct a data center...
joliet junior college logo

JJC Board Censures Trustee Broderick Twice, Denies Request to Restore Good Standing

Joliet Junior College Meeting | November 12, 2025 Article Summary:In a series of contentious votes, the Joliet Junior College Board of Trustees censured Trustee Maureen Broderick for two separate alleged...
mental health awareness day bipolar disorder anxiety stress emot

Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board on Thursday, October 16, 2025, approved a $10 million tax levy for the Community Mental Health...
The Wild Flowe rFarm

Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit

Will County Board Regular Meeting | October 16, 2025 Article Summary: Bengston Land Management, LLC, operators of The Wildflower Farm in Green Garden Township, received a second 180-day extension from the...
Screenshot 2025-10-17 at 3.14.53 PM

Will County Board Rejects Proposed Tax Hike, Approves 0% Levy Increase in Contentious Vote

Will County Board Regular Meeting | October 16, 2025 Article Summary: In a significant move providing relief to taxpayers, the Will County Board on Thursday, October 16, 2025, voted to approve...
Screenshot 2025-10-17 at 3.14.41 PM

Will County Awards $10.4 Million Contract for Bell Road Widening Project

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board has approved a $10.4 million contract with P.T. Ferro Construction Co. for a major roadway widening...
Screenshot 2025-10-17 at 3.15.09 PM

Regional Office of Education Highlights School Safety, New Learning Programs in Update

Will County Board Regular Meeting | October 16, 2025 Article Summary: Will County Regional Superintendent Dr. Lisa Caparelli-Ruff updated the County Board on key initiatives, including the installation of shooter-resistant window...