Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.36.47 AM

Will County to Draft First-Ever Policy on Artificial Intelligence Use

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: The Will County Board's Capital Improvements & IT Committee has initiated the process of drafting a comprehensive...
Screenshot 2025-10-10 at 11.20.18 AM

Will County Sees 50% Drop in Opioid Deaths, But Alarming Rise in Suicides

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is experiencing a dramatic 50% reduction in opioid overdose deaths compared to last year, a...
Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
Meeting Briefs

Meeting Summary and Briefs: Jackson Township Board for August 13, 2025

The Jackson Township Board took the next step in reviewing a proposed anaerobic digester project at its meeting on Wednesday, August 13, 2025, referring the plan from Elwood81, LLC, to...
Jackson Township

Jackson Township to Investigate Decade-Old High-Speed Rail Plan Through Elwood

Article Summary: Jackson Township officials are seeking information on a high-speed rail plan dating back to 2012 that would route a passenger line through the Elwood area. Supervisor Matt Robbins...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for August 14, 2025

The Manhattan Park Board made significant progress on its flagship Round Barn Farm project during its meeting on August 14, 2025. Commissioners unanimously approved hiring a new architect, Arete Design...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
jackson township graphic.1

Jackson Township Approves Settlement with Joliet, Union Pacific Over ICC Case

Article Summary: The Jackson Township Board unanimously approved a settlement agreement involving the City of Joliet and Union Pacific Railroad, formally resolving a multi-year case before the Illinois Commerce Commission....
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...