Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for June 2025

Manhattan Township Meeting | June 2025 The Manhattan Township Board passed its two largest annual fiscal items on Tuesday, June 10, 2025, unanimously approving township and road district budgets that...
Manhattan Township

Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete

Manhattan Township Meeting | June 2025 Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
Manhattan Township

Manhattan Township Donates $3,000 to Will County Community Concerns

Manhattan Township Meeting | June 2025 Article Summary: The Manhattan Township Board voted to donate $3,000 to the Will County Community Concerns agency, which has provided over $43,000 in direct financial...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...
Meeting Briefs

Meeting Summary: New Lenox Board of Trustees for July 14, 2025

The New Lenox Village Board of Trustees met Monday to approve site plans for a new business, waive fees for community projects, and hear a glowing report on the new...
Manhattan Township

Manhattan Township, Road District Approve Budgets Totaling Over $3.1 Million

Manhattan Township Meeting | June 2025 Article Summary: The Manhattan Township Board unanimously approved separate budgets for the township and the road district for the 2025-2026 fiscal year, appropriating over $3.1...
Police Crime

Manhattan Police Report

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On July 16th, officers were in the...