Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln way school district.3

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...
Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for April 14, 2025

The Frankfort Township Board of Trustees met on Monday, April 14, 2025, to address zoning matters and new business. The board took a firm stance against government consolidation, unanimously passing...
Manhattan Township

Manhattan Township Recommends Denial of Bruns Road Rodeo Permit Amid Neighbor Objections

The Manhattan Township Board unanimously recommended that Will County deny a permit for a large-scale commercial rodeo on Bruns Road, following a contentious public hearing where neighbors cited a history...
Manhattan Township

Road Contract Awarded as Township Races Against Bridge Funding Deadline

The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a...
Manhattan Township

Manhattan Township Halts Electric Aggregation Program, Citing Poor Pricing

Residents in unincorporated Manhattan Township will no longer be enrolled in a group electricity purchasing plan after the Township Board voted unanimously not to renew its electric aggregation contract. The...
Manhattan Township

Meeting Briefs: Manhattan Township for April 8, 2025

Assessor’s Office to Replace Server, Receives New Tax Multiplier: Assessor Joe Oldani reported that the township’s server is not compliant with current security methods and must be replaced by the end...
MFPD-Logo-Fire District

Fire District Receives Clean Audit, Adds 9 New Firefighters Despite Staff Departures

The Manhattan Fire Protection District received a clean audit report for fiscal year 2023 while addressing staffing challenges with nine new part-time firefighters set to join the department at the...
MFPD-Logo-Fire District

Construction Manager Decision Delayed for New Fire Station Project

The Manhattan Fire Protection District has postponed a decision on hiring a construction management company for its new fire station project while fee structures are finalized. Board members met with...
MFPD-Logo-Fire District

Manhattan Fire District March 17 Meeting Briefs

Vehicle Updates Progressing: The new Tahoe ordered last year has arrived but will require several months before entering service. The ambulance damaged in December's crash is currently at the body...
Manhattan Township

Manhattan Township to Fight State Consolidation Bills, Citing Threat to Local Services

The Manhattan Township Board is mounting a formal opposition to a series of state bills that officials believe threaten the existence of township governments across Illinois. During their monthly meeting...