Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Screenshot 2026-02-22 at 5.06.42 PM

Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board approved the appointments of a new Chief of Staff and a Dean of Workforce...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
manhattan elwood library graphic.5

Library Board Proposes Land-for-Services Swap with Village of Elwood for Mississippi Lot

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: The Manhattan-Elwood Public Library District Board voted to offer a piece of property to the Village of Elwood in exchange...
Jackson Township Graphic.1 NEW

Meeting Summary and Briefs: Jackson Township Board for January 14, 2026

Jackson Township Board Meeting | January 14, 2026 The Jackson Township Board of Trustees met for its regular monthly meeting on January 14, 2026, at the Jackson Township Hall. Supervisor...
Screenshot 2026-03-22 at 12.12.19 PM

Winter Benchmark Data Highlights Growth in Reading and Math Across Manhattan District 114

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: Manhattan School District 114 administrators presented winter benchmark data showing strong academic growth across all grade levels, with significant...
Screenshot 2026-02-22 at 4.29.56 PM

Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board of Education approved a $479,526.96 contract with CDW to replace the indoor wireless access points...
Committee-Executive.Graphic

Executive Committee: Tension Rises as Republican Whip Removed from Panel

Will County Executive Committee Meeting | February 11, 2026 Article Summary: A dispute over committee appointments erupted when Republican leadership challenged the removal of Member Vince Logan from the Executive...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: County Stripped of Power to Regulate Motor Races, Must Drop Solicitor Fees Due to State Statutes

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee repealed county regulations regarding motor stunt events and removed...

Commission Overrides Staff Recommendation, Approves Manhattan Township Barn Expansion

Will County Planning and Zoning Commission Meeting | February 17, 2026 Article Summary: A Manhattan Township homeowner received unanimous approval for three variances to expand a pole barn, despite county...
Untitled design - 1

Manhattan-Elwood Library Board Approves Over $21,000 for Playroom Renovation and Picture Book Shelving

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: The Manhattan-Elwood Public Library District Board authorized over $21,000 in youth facility upgrades, funding a playroom renovation and the purchase...
Manhattan Township

Meeting Summary and Briefs: Manhattan Township for January 13, 2026

Manhattan Township Meeting | January 13, 2026 The Manhattan Township Board of Trustees held its regular monthly meeting on Tuesday evening to review administrative transitions, process grant paperwork, and approve...
Jackson Township Graphic.1 NEW

Jackson Township Board Approves Elwood Baseball Donation, Reviews Food Pantry Transition

Jackson Township Board Meeting | January 14, 2026 Article Summary: The Jackson Township Board approved a $1,000 donation to the Elwood Baseball & Softball Association and received an update on...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board for February 17, 2026

Village of Manhattan Board Meeting | February 17, 2026 Overall Meeting SummaryThe Manhattan Village Board of Trustees met on Tuesday, February 17, 2026, to address infrastructure planning, intergovernmental cooperation, and...
Committee-Executive.Graphic

Executive Committee Advances “Project Northwinds”: 2,475 Jobs and $346 Million Investment Proposed for Former Caterpillar, Lion Electric Sites

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Will County Board Executive Committee moved forward a resolution supporting a massive manufacturing project that promises nearly 2,500...
Committee-Land Use.Graphic

Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use Committee approved special use permits for two businesses in Frankfort and...