Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Spread the love

Will County Land Use & Development Committee Meeting | March 5, 2026

Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved a special use permit for a 4.98-megawatt commercial solar energy facility on West Eagle Lake Road in Will Township.

Eagle Lake Road Solar Key Points:

  • The facility will utilize 52.65 acres of an 80.65-acre parcel zoned A-1 Agricultural (PIN # 20-21-08-200-001-0000).

  • Developer Synergy Power (Cenergy Power) anticipates generating $20,000 to $25,000 annually in local property taxes.

  • The project includes a $200,000 community benefit allocation and promises 10% to 20% utility bill credits for local community solar subscribers.

  • The approval includes two variances allowing ground cover to grow up to 36 inches and reducing mandatory mowing to twice a year to promote pollinator habitats.

The Will County Land Use and Development Committee on Thursday, March 5, 2026, unanimously approved Zoning Case ZC-25-112, granting a special use permit for a new commercial solar farm just outside the Village of Peotone.

The 4.98-megawatt facility, managed by Cenergy Power (operating as Synergy Power), will feature approximately 9,800 panels on 52.65 acres of a larger 80-acre parcel located at 5949 W. Eagle Lake Road in Will Township. The project represents the second phase of development on the site; the northern 20 acres were previously approved for solar development in 2025.

The application arrived at the committee following a 2-2 tie vote by the Will County Planning and Zoning Commission (PZC). According to county staff, only four of the seven PZC commissioners attended the previous hearing, resulting in a deadlock after a local farmer objected to the continued loss of agricultural land.

However, Chad Jabazi, representing the developer, alleviated the committee’s concerns by outlining the project’s financial and environmental benefits.

“We’re setting aside $200,000 for the donations for these projects, and one of the groups that we’re talking to is Will Township,” Jabazi told the committee, adding that the project will also generate between $20,000 and $25,000 annually in codified property tax revenue. “I just want to point out that this is a community solar project. So each of the residents locally that subscribe to this project at no cost… will receive anywhere from 10 to 20% bill credit savings.”

Board Member Sherry Newquist questioned how construction equipment would access the site, noting that portions of Eagle Lake Road are gravel and difficult to navigate. Jabazi confirmed the developer will secure a road use agreement with Will Township Road Commissioner Bruce Hamann and will pay to build up the necessary access roads at the company’s expense.

Additionally, the developer must secure a crossing agreement with Enbridge to traverse a 100-foot-wide crude oil pipeline easement that cuts diagonally across the property.

Board Member Judy Ogalla confirmed with the developer that all connectivity lines will be buried underground and that the site will feature native pollinator plants rather than utilizing grazing sheep for vegetation control.

According to the agenda packet, the project is technically situated within the ultimate footprint of the proposed South Suburban Airport. However, county staff noted the parcel sits within the second phase of the airport’s buildout, an expansion that staff remarked will “probably never happen.”

The committee voted 6-0 to approve the special use permit and its associated variances.

Leave a Comment





Latest News Stories

Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
MH 114 June 2

Manhattan School Board Approves Staff Changes, Healthcare Extension in Special Session

Manhattan School District 114's Board of Education approved several personnel changes and a healthcare extension during a special meeting Monday evening, conducting most of its business in closed session. The...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting Briefs

School District 114 June 2 Meeting Briefs

Staff Departures: Manhattan School District 114 accepted the resignations of Emily Corcoran and Caroline Pesa-Miller, both effective at the end of the 2025 school year. The board approved both resignations...
Meeting Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
MH VB 5--22

Manhattan Board Changes Meeting Time, Limits Public Comment

Village moves to 5:30 p.m. start time and reduces speaking period from five to three minutes The Village of Manhattan Board of Trustees approved two ordinance changes Tuesday that will...
MH VB 5--22

Manhattan Challenges Neighboring Villages to Pop Tab Competition

Community fundraising effort for Ronald McDonald House expands to include multiple villages The Village of Manhattan has officially challenged neighboring communities to a summer-long pop tab collection competition benefiting the...
Meeting Briefs

Manhatttan Village Board Meeting Briefs

MUNICIPAL UPDATES Memorial Day Services Planned: The I Honor Banner Ceremony will take place Sunday at 10 a.m. at the Manhattan Township Building, 230 S. Wabash Street. The ceremony dedicates...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
MFPD-Logo-Fire District

Fire Station Construction Bids Due June 3, Storm Generates 40 Emergency Calls

The Manhattan Fire Protection District has received strong interest from contractors for its new fire station project, with construction bids due back June 3 and groundbreaking still targeted for July....
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
MFPD-Logo-Fire District

Fire District Maintains Strong Call Volume, Equipment Readiness

The Manhattan Fire Protection District is maintaining steady emergency response capabilities while addressing routine equipment maintenance needs across its two-station operation. Deputy Chief Dave Piper's April operational report showed continued...