Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township
Will County Public Works and Transportation Committee Meeting | March 3, 2026
Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to “D” Construction for a complete bridge replacement over Forked Creek.
Scheer Road Bridge Key Points:
-
The $1,596,116.16 contract was awarded to Coal City-based “D” Construction, Inc.
-
The project involves the removal of the existing bridge and construction of a new single-span concrete beam bridge.
-
The work on Scheer Road over Forked Creek is located in Green Garden Township (County Board Districts 2 and 3).
-
Construction will require a full roadway closure from April through September 2026.
The Will County Public Works and Transportation Committee on Tuesday, March 3, unanimously confirmed the award of a massive infrastructure contract to replace the aging Scheer Road bridge in Green Garden Township.
The $1,596,116.16 contract was awarded to “D” Construction, Inc., out of Coal City, which submitted the lowest qualified bid during the February 18 letting. The project will be funded through a combination of the Road District’s allotment of Motor Fuel Tax (MFT) funds and County Bridge Tax funds.
The comprehensive project (Section 21-07104-02-BR) will take place on Scheer Road over Forked Creek, impacting County Board Districts 2 and 3.
According to the project summary provided in the agenda packet, the scope of work consists of the complete removal of the existing bridge structure. In its place, crews will construct a new single-span concrete beam bridge. The project also entails installing new full-depth hot-mix asphalt pavement approaching the bridge, reconstructing the aggregate approach chip and seal north of the bridge, and adding new aggregate shoulders, guardrails, and riprap.
The road will be completely closed during the construction period. Work is estimated to begin in April 2026, with an estimated completion date of September 25, 2026.
The committee passed the resolution confirming the award without opposition.
Latest News Stories
Illinois quick hits: Illinois U.S. senators split on shutdown vote
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for October 2025
Will County Saves Nearly $5.74 Million in Bond Refinancing, Explores Future Borrowing Options
Will County Board Advances New Speed Limits in Green Garden and Frankfort Townships
New Lenox Garage Variance Denied After Neighbor Cites ‘Massive’ Scale and Neighborhood Impact
Library Board Adopts New Cell Phone Stipend Policy for Employees
Manhattan Announces Proposed 6% Property Tax Levy Increase
JJC Celebrates “Future Wolves” Partnerships with Joliet and Troy School Districts
State Veto Session Passes Energy Bill Limiting County Zoning, Approves Toll Hike for Mass Transit
Commission Approves Peotone-Area Farmhouse Split, Overruling Staff’s “Spot Zoning” Concerns
Will County Finance Committee Hits Impasse on 2025 Tax Levy, Postpones Budget Votes
Manhattan Park Board Tables Decision on Site Plan for Potential Development