Will County Land Use & Development Committee Meeting | March 5, 2026

Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized zoning cases, giving developers in Peotone, Joliet, Wilmington, and Monee more time to navigate federal tax policy changes and secure final building permits.

Zoning Extension Key Points:

  • Trajectory Energy Partners received a third extension for a Peotone solar farm (SEXT-26-001) due to delays caused by recent federal renewable tax credit changes.

  • Alexander Norbertus Kuypers received a second extension (SEXT-26-002) for a Peotone construction sales business, passing in a 5-1 split vote.

  • Four solar projects in Joliet and Monee townships managed by Madison Energy and Nexamp received extensions as they finalize state and local permits.

The Will County Land Use and Development Committee on Thursday, March 5, 2026, cleared a backlog of administrative hurdles, approving extensions for seven major zoning projects that have been stalled by federal red tape and interagency permitting delays.

The most heavily discussed extension involved SEXT-26-001, a third extension request for Prairie Solar LLC (Trajectory Energy Partners) regarding a previously approved solar farm on West Kennedy Road in Peotone Township.

Matt Kapinsky, representing Trajectory Energy, explained that the project was derailed by recent sweeping changes to federal renewable energy tax policies.

“The federal tax credits that have been in place for a very long time were repealed and they were set under sort of a phase-out schedule,” Kapinsky explained. “It took, after that passage, some time for just about every financing party in the entire country to get comfortable with how that was going to shake out in terms of when they were going to be eligible, how they were going to potentially procure equipment, and get equipment safe-harbored.”

The committee unanimously granted the 180-day extension, extending the special use permit through August 8, 2026.

The committee also reviewed SEXT-26-002, a second extension for Alexander Norbertus Kuypers to operate a construction sales and services business at 11233 W. Kennedy Road in Peotone. Staff noted the applicant is merely waiting on the Illinois Department of Transportation (IDOT) to issue a final site development permit.

While the extension passed 5-1, Board Member Judy Ogalla voted against it. “Just the proximity of this to residential areas… there’s three or four houses right there. Because of that, I’m going to be a no,” Ogalla stated.

The committee subsequently issued unanimous extensions for the following five solar energy facilities:

  • SEXT-26-003: A first extension for New Energy Equity (Wild Cat Solar 3) at State Route 53 and S. 216th Avenue in Wilmington.

  • SEXT-26-004: A second extension for Madison Energy (formerly Dart Farms) at Cherry Hill Road and US 52 in Joliet Township.

  • SEXT-26-005: A second extension for Madison Energy at Cherry Hill Road and W. Schweitzer Road in Joliet Township.

  • SEXT-26-006: A first extension for Nexamp (formerly Dralle Sun LLC) on the north side of Dralle Road, west of I-57 in Monee Township.

  • SEXT-26-007: A first extension for Nexamp (formerly Dralle Sun 2 LLC) southeast of S. Ridgeland Avenue and West Dralle Road in Monee Township.

Representatives for both Madison Energy and Nexamp confirmed they have executed agreements with the Will-South Cook Soil & Water Conservation District to ensure native, pollinator-friendly plantings are installed at their respective sites.

Leave a Comment





Latest News Stories

MH 114 SB July 9, 2025

Manhattan 114 Board Hires New Teachers, Accepts Staff Resignations

The Manhattan School District 114 Board of Education approved the hiring of four certified teachers and three non-certified staff members for the upcoming school year during its meeting on July...
MH 114 SB July 9, 2025

District 114 Approves Federal Plan as Construction Nears Finish Line

The Manhattan School District 114 Board of Education took a key step in securing federal funding for the next fiscal year and received positive updates on the final stages of...
Meeting Briefs

Meeting Briefs: Manhattan School District 114 for July 9, 2025

Junior High Announces Mascot Debut, Community Events: Manhattan Junior High School is preparing to introduce its new mascot, “Demo,” at the PTO’s Back to School Bash on August 15 from 5:00...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...
Will-County-Land-Use-July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department May Seek Property Tax Increase to Maintain Critical Services

The Will County Health Department is grappling with significant budget shortfalls as multiple federal grants have been terminated or reduced, potentially forcing the agency to seek additional property tax revenue...
Will-County-Land-Use-July-3.1

Crete Township Solar Project Approved Despite Township Objections

A 21-acre commercial solar project in Crete Township received a favorable recommendation from the Will County Land Use and Development Committee on Thursday, despite an official objection from the township....
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Opens Second Breast Milk Depot in Bolingbrook

The Will County Health Department has opened its second breast milk depot in partnership with Mother's Milk Bank of the Western Great Lakes, expanding access to donated breast milk for...
Will-County-Land-Use-July3.2

Lockport Township Solar Farm Gains Committee Approval

The Will County Land Use and Development Committee on Thursday approved a special use permit for a 25-acre commercial solar energy facility in Lockport Township. The project, proposed by Daniel...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Plans Back-to-School Fair July 12

The Will County Health Department will host a Back-to-School Health Fair Saturday, July 12, from 10 a.m. to 2 p.m. at the Community Health Center, 1106 Neal Ave., Joliet. The...
Meeting Briefs

Meeting Briefs: Will County Land Use & Development Committee for July 3, 2025

Green Garden Township Rezoning for Future Subdivision ApprovedThe committee recommended approval of a map amendment for an 81-acre property on South 88th Avenue in Green Garden Township. The applicant, represented...
Meeting Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
MH VB 7-1

Manhattan awards $1.9M contract for Eastern Avenue rebuild

The Village of Manhattan Board approved a $1.94 million contract with PT Ferrell Construction for the reconstruction of Eastern Avenue from North Street to Smith Road during their July 1...