Manhattan District 114 Approves Asphalt and Door Contracts Amid Sweeping Summer Facilities Upgrades

Spread the love

Manhattan School District 114 Meeting | March 25, 2026

Article Summary: The Manhattan School District 114 Board of Education reviewed extensive capital improvement plans and approved specialized contracts for paving and door replacements across multiple campuses to address audits and aging infrastructure.

Manhattan District 114 Capital Projects Key Points:

  • The board unanimously approved an asphalt and curb installation contract with PT Ferro at Manhattan Junior High School, with completion targeted before graduation.

  • A separate independent contractor agreement was approved for door replacements at Anna McDonald and Manhattan Intermediate School to address 10-year audit findings.

  • Facilities staff are preparing for an estimated $105,000 HVAC repair project at Wilson Creek this summer, which will be funded through bond proceeds.

  • The district is advancing phase two of an LED lighting transition, utilizing ComEd incentives to replace outdated pendant and classroom lighting.

The Manhattan School District 114 Board of Education on Wednesday, March 25, 2026, laid the groundwork for a busy season of summer capital projects, unanimously approving two immediate infrastructure contracts while reviewing a slate of upcoming facility maintenance initiatives.

The special meeting heavily featured updates from Ryan McWilliams of the district’s building and grounds department, who provided a comprehensive rundown of the summer maintenance schedule and ongoing vendor negotiations.

The board took direct action on two immediate projects. First, the board unanimously approved an independent contractor agreement for door replacements at Anna McDonald and Manhattan Intermediate School (MIS). The work, scheduled for July, is a direct response to issues flagged during the district’s recent 10-year life safety audit. Board Member Brian Anderson noted that the project will replace numerous exterior hinges at the intermediate school that are currently failing and leaking hydraulic fluid.

The board also approved a contract with PT Ferro for asphalt and curb installation at Manhattan Junior High School. The paving project will focus on the concession area, and McWilliams indicated that a secondary phase involving a retaining wall will be brought to the board for approval in April. District officials noted they are pushing to have the area finished in time for the regional track meet and graduation ceremonies.

Beyond the approved contracts, McWilliams briefed the board on larger, looming infrastructure needs, specifically regarding HVAC and roofing systems.

The district recently conducted walkthroughs with 2010 Engineering to evaluate the heating and cooling systems at Anna McDonald and MIS. The engineering firm is currently drafting a full scope of work, which is expected to be substantial. McWilliams warned the board that if the firm recommends full boiler replacements, the project cost will increase significantly, likely reaching into the seven figures.

In the interim, the district plans to tackle a smaller HVAC stabilization project at Wilson Creek this summer. McWilliams described the work as a “non-intrusive” replacement of aging valves and actuators to rectify climate control issues. The project is estimated to cost around $105,000 and will likely be funded through available bond proceeds since it was not explicitly budgeted for the current fiscal cycle. At the same time, preventative maintenance is actively underway at Wilson Creek, with Johnson Controls wrapping up a three-day service to remove scaling and rust buildup from the building’s chillers.

“We got to make sure that we’re keeping the equipment that we have working effectively and efficiently,” McWilliams told the board.

The district is also pushing forward with phase two of its LED lighting transition. Having completed the initial phase, the district will now focus on replacing pendant lighting in the MIS library and old band room, as well as executing a complete lighting overhaul at Anna McDonald.

At Wilson Creek, the district plans to replace 4-foot fixtures with modern 2×2 drop-in LED panels across all classrooms. The upgraded system will feature motion sensors that automatically dim or shut off lights when a room has been empty for 15 minutes, generating long-term electricity savings calculated by ComEd’s energy incentive algorithms.

Additionally, the board discussed ongoing discussions with STR and Anthony Roofing regarding potential roof replacements or specialized coatings at the district’s buildings, though the project remains in a holding pattern as administrators weigh the considerable price differences between the two methods.

Finally, to manage the district’s outdoor athletic facilities, McWilliams reported the acquisition of a specialized John Deere ride-on field grooming machine. Sourced from Georgia after learning about the model from the New Lenox Rebels baseball organization, the machine is equipped with spike drags, a finishing drag, and a front plow to maintain the district’s baseball and softball fields.

Leave a Comment





Latest News Stories

diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
District 114 Bus

Parents Voice Alarms Over Bus Safety, Lateness in Manhattan School District

Article Summary: Parents raised serious transportation safety and reliability concerns at the Manhattan School District 114 board meeting, including a harrowing account of a kindergartener being dropped off at the...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for September 16, 2025

The Manhattan Village Board took steps to prepare for future growth at its Tuesday meeting, awarding a contract of over half a million dollars to extend water and sewer infrastructure...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
Screenshot 2025-09-27 at 8.39.48 AM

Manhattan Police Department Promotes Garrison to Commander, Diaz to Sergeant

Article Summary: The Manhattan Police Department solidified its command structure with the promotions of William Garrison to the rank of Commander and Bryan Diaz to Sergeant, who were both officially...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for August 18, 2025

Manhattan Fire Protection District | August 18, 2025 Meeting The Manhattan Fire Protection District Board of Trustees focused on the future of its facilities and public safety at its meeting...
Screenshot 2025-09-27 at 8.36.16 AM

Village of Manhattan Honors St. Joseph’s Catholic School on its 100th Anniversary

Article Summary: The Village of Manhattan celebrated a major community milestone at its Tuesday board meeting, officially honoring St. Joseph's Catholic School for its 100th anniversary with a formal proclamation...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Screenshot 2025-09-27 at 8.36.16 AM

Manhattan Awards $547K Contract for US 52 Infrastructure Extension to Spur Growth

Article Summary: The Village of Manhattan has awarded a $547,449 contract to Speece Construction for a significant sewer and water main extension project along the US 52, Smith Road, and...
manhattan fire district graphic logo.3

Fire District to Address Safety at High-Accident Intersections with County DOT

Manhattan Fire Protection District | August 18, 2025 Meeting Article Summary: The Manhattan Fire Protection District will meet with the Will County Department of Transportation to provide data and seek...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for August 2025

Manhattan Township Meeting | August 2025 The Manhattan Township Board took steps to address the growing interest in renewable energy at its meeting on Tuesday, August 12, 2025, by scheduling...
Screenshot 2025-09-27 at 8.16.09 AM

Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate...