Manhattan District 114 Approves Asphalt and Door Contracts Amid Sweeping Summer Facilities Upgrades

Spread the love

Manhattan School District 114 Meeting | March 25, 2026

Article Summary: The Manhattan School District 114 Board of Education reviewed extensive capital improvement plans and approved specialized contracts for paving and door replacements across multiple campuses to address audits and aging infrastructure.

Manhattan District 114 Capital Projects Key Points:

  • The board unanimously approved an asphalt and curb installation contract with PT Ferro at Manhattan Junior High School, with completion targeted before graduation.

  • A separate independent contractor agreement was approved for door replacements at Anna McDonald and Manhattan Intermediate School to address 10-year audit findings.

  • Facilities staff are preparing for an estimated $105,000 HVAC repair project at Wilson Creek this summer, which will be funded through bond proceeds.

  • The district is advancing phase two of an LED lighting transition, utilizing ComEd incentives to replace outdated pendant and classroom lighting.

The Manhattan School District 114 Board of Education on Wednesday, March 25, 2026, laid the groundwork for a busy season of summer capital projects, unanimously approving two immediate infrastructure contracts while reviewing a slate of upcoming facility maintenance initiatives.

The special meeting heavily featured updates from Ryan McWilliams of the district’s building and grounds department, who provided a comprehensive rundown of the summer maintenance schedule and ongoing vendor negotiations.

The board took direct action on two immediate projects. First, the board unanimously approved an independent contractor agreement for door replacements at Anna McDonald and Manhattan Intermediate School (MIS). The work, scheduled for July, is a direct response to issues flagged during the district’s recent 10-year life safety audit. Board Member Brian Anderson noted that the project will replace numerous exterior hinges at the intermediate school that are currently failing and leaking hydraulic fluid.

The board also approved a contract with PT Ferro for asphalt and curb installation at Manhattan Junior High School. The paving project will focus on the concession area, and McWilliams indicated that a secondary phase involving a retaining wall will be brought to the board for approval in April. District officials noted they are pushing to have the area finished in time for the regional track meet and graduation ceremonies.

Beyond the approved contracts, McWilliams briefed the board on larger, looming infrastructure needs, specifically regarding HVAC and roofing systems.

The district recently conducted walkthroughs with 2010 Engineering to evaluate the heating and cooling systems at Anna McDonald and MIS. The engineering firm is currently drafting a full scope of work, which is expected to be substantial. McWilliams warned the board that if the firm recommends full boiler replacements, the project cost will increase significantly, likely reaching into the seven figures.

In the interim, the district plans to tackle a smaller HVAC stabilization project at Wilson Creek this summer. McWilliams described the work as a “non-intrusive” replacement of aging valves and actuators to rectify climate control issues. The project is estimated to cost around $105,000 and will likely be funded through available bond proceeds since it was not explicitly budgeted for the current fiscal cycle. At the same time, preventative maintenance is actively underway at Wilson Creek, with Johnson Controls wrapping up a three-day service to remove scaling and rust buildup from the building’s chillers.

“We got to make sure that we’re keeping the equipment that we have working effectively and efficiently,” McWilliams told the board.

The district is also pushing forward with phase two of its LED lighting transition. Having completed the initial phase, the district will now focus on replacing pendant lighting in the MIS library and old band room, as well as executing a complete lighting overhaul at Anna McDonald.

At Wilson Creek, the district plans to replace 4-foot fixtures with modern 2×2 drop-in LED panels across all classrooms. The upgraded system will feature motion sensors that automatically dim or shut off lights when a room has been empty for 15 minutes, generating long-term electricity savings calculated by ComEd’s energy incentive algorithms.

Additionally, the board discussed ongoing discussions with STR and Anthony Roofing regarding potential roof replacements or specialized coatings at the district’s buildings, though the project remains in a holding pattern as administrators weigh the considerable price differences between the two methods.

Finally, to manage the district’s outdoor athletic facilities, McWilliams reported the acquisition of a specialized John Deere ride-on field grooming machine. Sourced from Georgia after learning about the model from the New Lenox Rebels baseball organization, the machine is equipped with spike drags, a finishing drag, and a front plow to maintain the district’s baseball and softball fields.

Leave a Comment





Latest News Stories

WCO-PZ-Aug-5.2

Homer Glenn Residents Push Back on 143rd Street Widening as Officials Signal “Tentative Agreement”

ARTICLE SUMMARY: A Homer Glenn farm owner voiced strong opposition to the planned widening of 143rd Street during a county meeting, while committee members indicated a "tentative agreement" is in the...
WCO-LEG-8.5.1

Will County Forges 2026 Federal Agenda Amid D.C. Policy Shifts, ‘Big Beautiful Bill’ Impacts

ARTICLE SUMMARY: The Will County Board's Legislative Committee is reshaping its federal priorities for 2026, adding new language on environmental justice and LGBTQIA+ rights while creating a more transparent process for...
WCO-Public-Safety.3

Health Department Seeks $1 Million Levy Increase to Prevent “Weakened System”

Article Summary: The Will County Health Department is asking for a $1 million increase to its property tax levy to save 11 critical jobs that are at risk as post-pandemic...
WCO-Cap-Imp-8.5.3

County Rolls Out New “OneMeeting” Software to Improve Public Access

ARTICLE SUMMARY: Will County has officially launched a new agenda and meeting management software called "OneMeeting," aimed at improving transparency and making it easier for the public and officials to access...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for August 5, 2025

The Will County Board’s Finance Committee confronted major budget challenges during its Tuesday meeting, led by a stark presentation from the Will County Health Department. Health officials are requesting an...
WCO-PZ-8.12.2

Will County PZC Approves Rezoning for Truck Repair Facility on Manhattan Road Amid Resident Concerns

Article Summary: The Will County Planning and Zoning Commission voted 4-2 to rezone nearly 14 acres in Joliet Township for a truck repair facility. The approval came after a neighboring...
WCO-PZ-Aug-5.3

Key Stretch of Bell Road on Track for Thanksgiving Reopening, Committee Approves Additional Funds

ARTICLE SUMMARY Construction on Bell Road between 159th and 151st Streets is scheduled to have all lanes open by Thanksgiving, officials announced as the Public Works & Transportation Committee approved a...
WCO-LEG-8.5.2

Will County Leglislative Committee Opposes Federal Push for Heavier, Longer Trucks

ARTICLE SUMMARY: The Will County Board's Legislative Committee unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on national roadways. Will...
WCO-Public-Safety.2

Will County Reports Progress in Opioid Fight, Highlights New FDA Labeling Rules

Article Summary: Will County is seeing a reduction in opioid overdose deaths and is expanding access to the reversal drug Narcan, health officials reported. The department also drew attention to...
WCO-Cap-Imp-8.5.4

In-House Staff Completes Major Renovations at Will County Adult Detention Facility

ARTICLE SUMMARY: Maintenance staff at the Will County Adult Detention Facility recently completed extensive renovations in-house, including a new control center and the full restoration of a 48-cell housing unit, saving...
Land-use-8.5.25

Will County Advances Truck Repair Facility Plan on Manhattan Road Despite Resident Objections

Article Summary: A proposal to rezone nearly 14 acres on Manhattan Road for a truck repair facility advanced after receiving a recommendation for approval from the Will County Land Use...
WCO-PZ-8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO-PZ-Aug-5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...