Manhattan District 114 Approves Asphalt and Door Contracts Amid Sweeping Summer Facilities Upgrades

Spread the love

Manhattan School District 114 Meeting | March 25, 2026

Article Summary: The Manhattan School District 114 Board of Education reviewed extensive capital improvement plans and approved specialized contracts for paving and door replacements across multiple campuses to address audits and aging infrastructure.

Manhattan District 114 Capital Projects Key Points:

  • The board unanimously approved an asphalt and curb installation contract with PT Ferro at Manhattan Junior High School, with completion targeted before graduation.

  • A separate independent contractor agreement was approved for door replacements at Anna McDonald and Manhattan Intermediate School to address 10-year audit findings.

  • Facilities staff are preparing for an estimated $105,000 HVAC repair project at Wilson Creek this summer, which will be funded through bond proceeds.

  • The district is advancing phase two of an LED lighting transition, utilizing ComEd incentives to replace outdated pendant and classroom lighting.

The Manhattan School District 114 Board of Education on Wednesday, March 25, 2026, laid the groundwork for a busy season of summer capital projects, unanimously approving two immediate infrastructure contracts while reviewing a slate of upcoming facility maintenance initiatives.

The special meeting heavily featured updates from Ryan McWilliams of the district’s building and grounds department, who provided a comprehensive rundown of the summer maintenance schedule and ongoing vendor negotiations.

The board took direct action on two immediate projects. First, the board unanimously approved an independent contractor agreement for door replacements at Anna McDonald and Manhattan Intermediate School (MIS). The work, scheduled for July, is a direct response to issues flagged during the district’s recent 10-year life safety audit. Board Member Brian Anderson noted that the project will replace numerous exterior hinges at the intermediate school that are currently failing and leaking hydraulic fluid.

The board also approved a contract with PT Ferro for asphalt and curb installation at Manhattan Junior High School. The paving project will focus on the concession area, and McWilliams indicated that a secondary phase involving a retaining wall will be brought to the board for approval in April. District officials noted they are pushing to have the area finished in time for the regional track meet and graduation ceremonies.

Beyond the approved contracts, McWilliams briefed the board on larger, looming infrastructure needs, specifically regarding HVAC and roofing systems.

The district recently conducted walkthroughs with 2010 Engineering to evaluate the heating and cooling systems at Anna McDonald and MIS. The engineering firm is currently drafting a full scope of work, which is expected to be substantial. McWilliams warned the board that if the firm recommends full boiler replacements, the project cost will increase significantly, likely reaching into the seven figures.

In the interim, the district plans to tackle a smaller HVAC stabilization project at Wilson Creek this summer. McWilliams described the work as a “non-intrusive” replacement of aging valves and actuators to rectify climate control issues. The project is estimated to cost around $105,000 and will likely be funded through available bond proceeds since it was not explicitly budgeted for the current fiscal cycle. At the same time, preventative maintenance is actively underway at Wilson Creek, with Johnson Controls wrapping up a three-day service to remove scaling and rust buildup from the building’s chillers.

“We got to make sure that we’re keeping the equipment that we have working effectively and efficiently,” McWilliams told the board.

The district is also pushing forward with phase two of its LED lighting transition. Having completed the initial phase, the district will now focus on replacing pendant lighting in the MIS library and old band room, as well as executing a complete lighting overhaul at Anna McDonald.

At Wilson Creek, the district plans to replace 4-foot fixtures with modern 2×2 drop-in LED panels across all classrooms. The upgraded system will feature motion sensors that automatically dim or shut off lights when a room has been empty for 15 minutes, generating long-term electricity savings calculated by ComEd’s energy incentive algorithms.

Additionally, the board discussed ongoing discussions with STR and Anthony Roofing regarding potential roof replacements or specialized coatings at the district’s buildings, though the project remains in a holding pattern as administrators weigh the considerable price differences between the two methods.

Finally, to manage the district’s outdoor athletic facilities, McWilliams reported the acquisition of a specialized John Deere ride-on field grooming machine. Sourced from Georgia after learning about the model from the New Lenox Rebels baseball organization, the machine is equipped with spike drags, a finishing drag, and a front plow to maintain the district’s baseball and softball fields.

Leave a Comment





Latest News Stories

Manhattan School District 114 Logo Graphic

Manhattan District Adopts New Math Program After Comprehensive Review

The Manhattan School District 114 Board of Education unanimously approved the adoption of Eureka Math Squared for kindergarten through eighth grade on Tuesday, concluding a year-long evaluation process involving 25...
Manhattan School District 114 Logo Graphic

Manhattan Junior High Scholastic Bowl Team Places Second at State Championship

Manhattan Junior High School's scholastic bowl team achieved a historic milestone by placing second in the state championship, marking the first time in the program's eight-year history that the team...
Manhattan School District 114 Logo Graphic

Enrollment Growth Prompts Staffing Discussions as Construction Continues

Manhattan School District 114 continues managing significant enrollment growth while construction projects remain on schedule for completion by the end of the school year. Current kindergarten enrollment of 218 students...
Manhattan School District 114 Logo Graphic

School District 114 Meeting Briefs

Budget Display Scheduled: The district's fiscal year 2025 amended budget will be on public display from May 15 through June 17, with board approval scheduled for the June 17 meeting....
Manhattan Township

Manhattan Road District Eyes $2.1M Budget, Hinges on Unguaranteed Solar Farm Funds

The Manhattan Township Road District is proposing a $2.15 million budget for the upcoming fiscal year, a plan that includes the purchase of a new truck and finishing a storage...
Manhattan Township

Manhattan Township Delays Decision on Critical Server Upgrade Amid Security Concerns

Manhattan Township officials are weighing a costly but necessary technology upgrade after learning their primary server is a decade old and runs on unsupported software, posing a potential cybersecurity risk....
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
Manhattan Township

Assessor Announces End to “Empathetic” Tax Reductions, Raises Senior Freeze Threshold

Manhattan Township homeowners will see two significant changes in property assessment rules, including the end of a long-standing practice of granting tax reductions for fire-damaged properties and a beneficial increase...
Manhattan Township

Meeting Briefs: Manhattan Township for May 13, 2025

Officials Sworn into Office: Clerk Kelly Baltas administered the oath of office to newly elected and re-elected officials. Taking the oath were Supervisor James F. Walsh and Trustees Eileen Fitzer, Paul...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
Village of Manhattan Logo Graphic

Manhattan Swears In New Officials, Tables Fire Code Discussion

Village postpones St. Joseph's school sprinkler decision as benefactors emerge to help with costs Mayor Mike Adrieansen began his second term alongside newly elected Village Clerk Rebecca Bouck and trustees...
Village of Manhattan Logo Graphic

Manhattan Honors Departing Officials at Final Board Meeting

Beemsterboer, Adamski and Lewis recognized for combined 32 years of public service The Village of Manhattan honored three departing officials Tuesday evening, recognizing their combined 32 years of public service...
Village of Manhattan Logo Graphic

Manhattan Village Board Meeting Briefs

New Police Vehicles Approved: The village board authorized purchasing two new police interceptors for $157,362 total. A 2025 Ford F-150 will replace squad 773 for truck enforcement duties, while a...
MFPD-Logo-Fire District

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...