Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved a $1.98 million contract with CDW/Greatline Solutions to upgrade aging wired infrastructure at the Central and East campuses to support modern technology and faster network speeds.

Cabling Upgrade Key Points:

  • A contract for a total cost of $1,982,901.00 was awarded to CDW/Greatline Solutions.

  • The project replaces 20-to-25-year-old CAT 5e cabling with CAT 6A, supporting up to 10 gigabits per second.

  • The district anticipates receiving $480,000 in reimbursements through the federal E-Rate program.

  • The new cabling comes with a 25-year manufacturer warranty.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, unanimously approved a contract for a total cost of $1,982,901.00 with CDW/Greatline Solutions for a district-wide wired infrastructure upgrade.

The district issued a Request for Proposals (RFP) in January 2026 to upgrade components of its wired infrastructure through the federal E-Rate process. According to Director of Technology Cheryl Kay, much of the existing cabling at Lincoln-Way Central and East is 20 to 25 years old. The older CAT 5 and CAT 5e cabling standards do not support the faster speed capabilities of modern switching and wireless equipment recently purchased by the district.

“To put this into perspective for you, CAT 5e cabling supports speeds up to 1 gigabit per second, while CAT 6A cabling can support speeds up to 10 gigabits per second,” Kay explained to the Board. “I’ve used the garden hose versus the fire hose analogy in the past. So essentially, the new cabling allows more data to move through the network at one time.”

The upgraded infrastructure will also establish a foundation for future technology projects, including IP communication systems, digital signage, emergency alerting, and intercom systems that are nearing the end of their usable life.

The district received three proposals. While Netsource Solutions submitted a lower bid of $1,885,001.00, the district rejected it because the company only had 25 total employees. Kay noted that the district had significant concerns about a company of that size being able to complete the massive scope of work on time across multiple buildings. CDW/Greatline, a vendor the district has successfully used for past fiber projects, was selected instead.

The project is included in the district’s 5-year technology plan. Because a significant portion of the work qualifies for E-Rate reimbursements, the district anticipates receiving roughly $480,000 back after the project is completed. The installation work will be completed between April 1, 2026, and September 30, 2027, working around the district’s upcoming HVAC construction schedule.

Leave a Comment





Latest News Stories

IL U.S. Rep says health care crisis caused by failing to extend ACA tax credits

IL U.S. Rep says health care crisis caused by failing to extend ACA tax credits

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A Democratic Illinois congresswoman says Republicans have caused a health care crisis by not extending Affordable Care...
Judge declines CTU's motion to dismiss financial audit lawsuit

Judge declines CTU’s motion to dismiss financial audit lawsuit

By Dan McCaleb and Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A Cook County judge on Monday denied a Chicago Teachers' Union motion for summary...
Illinois pushes rate-hike protections forward despite consumer cost fears

Illinois pushes rate-hike protections forward despite consumer cost fears

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Home and auto insurance providers in Illinois could face new oversight and regulation after a Senate bill...
Illinois bill aims to delay 2024 tax sales, protect homeowners’ equity

Illinois bill aims to delay 2024 tax sales, protect homeowners’ equity

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers are weighing a proposal to delay property tax sales and pause penalties as the...
Illinois Quick Hits: Man on pretrial release charged with fireman's murder

Illinois Quick Hits: Man on pretrial release charged with fireman’s murder

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A Chicago man is charged with murder and aggravated arson in connection with a fire that killed...
Screenshot 2026-03-22 at 12.17.46 PM

Manhattan School District 114 Approves $5.75 Million Fund Transfer, Advances Bond Repayment

Manhattan School District 114 Meeting | March 11, 2026 Article Summary: The Manhattan School District 114 Board of Education held a public hearing and subsequently approved the transfer of $5.75...
Will County Board Graphic.04

Will County Targets May Draft for Comprehensive Artificial Intelligence Policy

Capital Improvements & IT Committee Meeting | March 2026 Article Summary:Will County is moving closer to adopting a formal Artificial Intelligence policy, with IT staff planning to deliver a comprehensive...
Manhattan Park District Graphic

Manhattan Park Board Abates Bond Taxes, Authorizes Legal Intervention in Large Tax Appeals

Manhattan Park Board Meeting | February 12, 2026 Article Summary: The Manhattan Park District Board of Commissioners passed a resolution authorizing legal counsel to intervene in property tax appeals exceeding...
Will County P&Z Logo Planning Zoning.2

P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a variance to reduce a side yard setback on...
Will County Board Graphic.01

Executive Committee Advances Sweeping Overhaul of Will County Business Regulations

Will County Executive Committee Meeting | March 12, 2026 Article Summary: Will County is poised to modernize its business regulations following the Executive Committee's unanimous approval of a massive ordinance overhaul....
manhattan fire district graphic logo.2

Manhattan Fire District Fills Full-Time Vacancy, Welcomes Part-Time Members and Interns

Manhattan Fire Protection District Meeting | February 17, 2026 Article Summary: Following a recent disability hearing, the Manhattan Fire Protection District is moving to fill an operational vacancy with a...
Will County Finance Logo

Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County has officially closed out its massive federal Emergency Rental Assistance program after distributing millions to keep nearly 2,000...
Will County P&Z Logo Planning Zoning

Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026

Will County Planning and Zoning Commission Meeting | March 3, 2026 Overall Meeting SummaryThe Will County Planning and Zoning Commission convened on Tuesday, March 3, 2026, to review a series...
will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Capital Improvements & IT Committee Meeting | March 2026 Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased...
manhattan fire district graphic logo.3

Meeting Summary and Briefs: Manhattan Fire Protection District for February 17, 2026

Manhattan Fire Protection District Meeting | February 17, 2026 The Manhattan Fire Protection District Board of Trustees held its regular meeting on Tuesday, February 17, 2026, at Fire Station #81....