Judge Orders Will County Board to Approve Previously Denied Solar Farm Permits
On Wednesday, Will County’s efforts to maintain local control over solar farm developments were dealt a heavy blow when 12th District Associate Judge Ben Braun ruled the County Board must approve several previously denied solar farm requests.
Braun’s long-awaited ruling combined lawsuits filed against the county by Channahon McKinley Woods, RPIL Solar 13, Florence Renewables LLC, NL Gougar Solar 1, Black Road Solar 1, and Black Road Solar 2. The judge ordered the county to approve all special use permits for the applications, many of which had previously been denied not only by the full board, but also by the board’s Land Use Committee and Planning and Zoning Commission.
The county has been ordered to comply with the ruling by April 17, 2026, with a court status hearing set for April 16. To meet the court’s mandate, County Board leaders are expected to place the previously denied permits on the agenda for their April 16 meeting.
The April 16 meeting agenda is already slated to be heavily focused on renewable energy. The board is scheduled to vote on two massive solar farm applications from Earthrise Energy: the 2,400-acre Plum Creek project and the nearly 6,100-acre Pride of the Prairie project. While the county’s Planning and Zoning Commission and the Land Use Committee recommended approving the smaller Plum Creek plan, both bodies recommended denying the Pride of the Prairie proposal.
Anticipating significant public interest, officials have moved the April 16 County Board meeting to the Clarion Hotel at South Larkin Avenue and McDonough Street in Joliet. Previous hearings for the Earthrise Energy plans have drawn large crowds largely in opposition to the developments.
Latest News Stories
District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service
Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025
Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall
Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases
Manhattan School District 114 Approves $41.5 Million Budget for FY26
Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers