Judge Orders Will County Board to Approve Previously Denied Solar Farm Permits
On Wednesday, Will County’s efforts to maintain local control over solar farm developments were dealt a heavy blow when 12th District Associate Judge Ben Braun ruled the County Board must approve several previously denied solar farm requests.
Braun’s long-awaited ruling combined lawsuits filed against the county by Channahon McKinley Woods, RPIL Solar 13, Florence Renewables LLC, NL Gougar Solar 1, Black Road Solar 1, and Black Road Solar 2. The judge ordered the county to approve all special use permits for the applications, many of which had previously been denied not only by the full board, but also by the board’s Land Use Committee and Planning and Zoning Commission.
The county has been ordered to comply with the ruling by April 17, 2026, with a court status hearing set for April 16. To meet the court’s mandate, County Board leaders are expected to place the previously denied permits on the agenda for their April 16 meeting.
The April 16 meeting agenda is already slated to be heavily focused on renewable energy. The board is scheduled to vote on two massive solar farm applications from Earthrise Energy: the 2,400-acre Plum Creek project and the nearly 6,100-acre Pride of the Prairie project. While the county’s Planning and Zoning Commission and the Land Use Committee recommended approving the smaller Plum Creek plan, both bodies recommended denying the Pride of the Prairie proposal.
Anticipating significant public interest, officials have moved the April 16 County Board meeting to the Clarion Hotel at South Larkin Avenue and McDonough Street in Joliet. Previous hearings for the Earthrise Energy plans have drawn large crowds largely in opposition to the developments.
Latest News Stories
Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win
Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Meeting Summary and Briefs: Manhattan-Elwood Public Library District for January 26, 2026
Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns
Manhattan School District Approves Tax Abatement and Fund Transfers
Contracts Approved for New West Principal and District Technology Director
Manhattan-Elwood Library Officially Adopts “Library of Things” Policies and Patron Waivers
Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026
Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency
Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm
Library Board Proposes Land-for-Services Swap with Village of Elwood for Mississippi Lot
Meeting Summary and Briefs: Jackson Township Board for January 14, 2026