Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Spread the love

Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

Manhattan Weather Full forecast →
Today Jun 5
Showers And Thunderstorms Likely
86° 65°

Showers And Thunderstorms Likely

💨 5 to 10 mph 💧 63%

Leave a Comment





Latest News Stories

Screenshot 2025-11-05 at 3.23.49 PM

Village Administrator Jeff Wold Resigns; Marc Nelson Appointed Interim

Manhattan Village Board Meeting | November 4, 2025 Article Summary: Manhattan Village Administrator Jeff Wold announced his resignation on Tuesday, November 4, 2025, to return to a career in law...
manhattan elwood library graphic.4

Manhattan-Elwood Library Board Reviews 2024-2025 Financial Audit

Manhattan-Elwood Public Library District Board Meeting | September 2025 Article SummaryThe Manhattan-Elwood Public Library District Board of Trustees received the results of its annual financial audit for the 2024-2025 fiscal...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
Joliet-Junior-college.-Graphic-Logo.4

JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees has authorized negotiations for a land acquisition to build a...
will county board graphic

Commission Grants Green Garden Solar Farm Project Variance Extension

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial...
Untitled design - 1

Manhattan-Elwood Library Board Approves Annual Tax Levy

Manhattan-Elwood Public Library District Board Meeting | September 2025 Article SummaryThe Manhattan-Elwood Public Library District Board of Trustees unanimously approved its 2025 tax levy following a public hearing on September...
Screenshot 2025-11-05 at 3.23.42 PM

Manhattan Adopts Downtown Design Guidelines to Unify and Revitalize Village Center

Manhattan Village Board Meeting | November 4, 2025 Article Summary: The Manhattan Village Board on Tuesday, November 4, 2025, unanimously approved a new set of Downtown Design Guidelines aimed at...
Will Dial-A-Ride Service

Will County Committee Advances Phased Takeover of Central Will Dial-A-Ride Service

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved a five-year plan to consolidate the Central Will Dial-A-Ride service into its...
Screenshot 2025-11-05 at 3.23.31 PM

Manhattan Grapples with Route 52 Safety After Tragedy, Demands Action from IDOT

Manhattan Village Board Meeting | November 4, 2025 Article Summary: Following a recent tragedy, the Manhattan Village Board on Tuesday, November 4, 2025, held an extensive public discussion on the...
manhattan park district graphic.2

Manhattan Park District Ratifies Emergency Purchase of Bucket Truck for $36,500

Manhattan Park Board Meeting | September 2025 Article Summary: The Manhattan Park Board has unanimously ratified the emergency purchase of a used 2012 Ram 5500 bucket truck for $36,500. The board...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for October 21, 2025

Will County Planning and Zoning Commission Meeting | October 21, 2025 The Will County Planning and Zoning Commission on Tuesday, October 21, 2025, tackled several high-profile land use issues, recommending...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 21, 2025

Will County Board Finance Committee Meeting | October 21, 2025 A contentious debate over a looming $8.9 million budget shortfall dominated the Will County Board Finance Committee meeting on Tuesday....
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for September 15, 2025

Manhattan Fire Protection District Meeting | September 15, 2025 The Manhattan Fire Protection District Board of Trustees took a major step toward building a new fire station at its meeting...