Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Leave a Comment





Latest News Stories

will county board meeting.6

Will County Expands Narcan Distribution Amid Shifts in Opioid Overdose Demographics

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: The Will County Health Department is ramping up its opioid overdose prevention efforts by distributing more...
Police Crime

Additional Skeletal Remains Discovered at Mokena Property

Article Summary: Law enforcement officials have secured a property in Mokena for an extended search after a secondary sweep of the area revealed additional skeletal remains near the site where...
Travis

Beecher Man Charged with 10 Felony Counts for Possession of Child Sex Abuse Material

Article Summary: A 45-year-old Beecher resident turned himself in to Will County Sheriff's deputies to face 10 felony counts related to the possession of child sexual abuse material following a...
Screenshot 2026-04-10 at 1.52.27 PM

Manhattan School District 114 Celebrates Historic State Placements for Wrestling, Music, and Bowling

Manhattan School District 114 Board of Education Meeting | April 8, 2026 Article Summary: The Manhattan School District 114 Board of Education recognized an unprecedented series of student achievements across...
solar panels photovoltaics in solar farm

Will County Legislative Committee Unanimously Backs Resolution Demanding Return of Local Solar Siting Control

Will County Board Legislative Committee Meeting | April 7, 2026 Article Summary: The Will County Board Legislative Committee unanimously passed an amended resolution on Tuesday demanding the Illinois General Assembly...
Perry House

Joseph Perry House Granted Historic Landmark Status

The committee unanimously approved a resolution (26-4451) designating the Joseph Perry House as a Will County Historic Landmark. Located at 365 W. Exchange Street in Crete Township (PIN # 23-15-09-318-016-0000),...
Will County Board Land Use Committee Graphic.3

Green Garden Township’s Wildflower Farm Granted Third Extension for Rural Events Permit

Will County Board Land Use & Development Committee Meeting | April 2, 2026 Article Summary: The Will County Land Use and Development Committee unanimously approved a third 180-day extension for...
Will County Board Graphic.04

Will County Lowers Cedar Road Speed Limit Amid Debate Over Curve Safety and Fatalities

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The Will County Public Works and Transportation Committee approved lowering a segment of Cedar Road to...
Will County Board Graphic.01

Nine Will County Municipalities Face Expired License Plate Reader Agreements; Crest Hill Opts Out

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County's network of Automatic License Plate Readers (ALPRs) is undergoing a renewal phase, with nine...
solar panels photovoltaics in solar farm

Judge Orders Will County Board to Approve Previously Denied Solar Farm Permits

On Wednesday, Will County’s efforts to maintain local control over solar farm developments were dealt a heavy blow when 12th District Associate Judge Ben Braun ruled the County Board must...
Lincoln Way West Warriors Softball

Lincoln-Way West Powers Past Cross-Town Rival Lincoln-Way Central in 11-1 Run-Rule Victory

The Lincoln-Way West varsity softball team utilized a potent, power-heavy offensive attack and flawless defense to defeat visiting Lincoln-Way Central 11-1 in a five-inning conference matchup on Thursday afternoon. Despite...
Lincoln Way West Warriors Baseball

Lincoln-Way East Pitching Shuts Down Lincoln-Way West in 4-0 Conference Victory

The Lincoln-Way East varsity baseball team leveraged a flawless defensive effort and a dominant pitching performance to blank visiting Lincoln-Way West 4-0 in a conference matchup on Thursday afternoon. While...
Screenshot 2026-04-08 at 3.23.31 PM

Manhattan Receives $10,000 JADA Grant, Approves Patriotic Route 52 Decorations

Village of Manhattan Board of Trustees Meeting | April 7, 2026 Article Summary: The Joliet Arsenal Development Authority presented the Village of Manhattan with a $10,000 check to promote local...
WATCH: California probe ends $267M in alleged hospice fraud

WATCH: California probe ends $267M in alleged hospice fraud

By Chris WoodwardThe Center Square California Attorney General Rob Bonta has announced the results of a massive hospice fraud bust in Los Angeles County. Known as Operation Skip Trace, the...
Ex-Blago attorney: Quid pro quo is key to Madigan appeal

Ex-Blago attorney: Quid pro quo is key to Madigan appeal

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A federal appeals court heard oral arguments Thursday as judges consider former Illinois House Speaker Michael Madigan’s...