Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Leave a Comment





Latest News Stories

Partial government shutdown looms after funding deal failure

Partial government shutdown looms after funding deal failure

By Thérèse BoudreauxThe Center Square The U.S. Senate failed to advance a package of the six remaining federal funding bills Thursday, leaving less than 40 hours until the federal government...
Lawmaker pushing bill to study insurance for gun owners

Lawmaker pushing bill to study insurance for gun owners

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Gun rights advocates in Illinois are raising alarms over House Bill 43, legislation that would create...
Illinois lawmakers consider bill to restrict SNAP buys

Illinois lawmakers consider bill to restrict SNAP buys

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers are considering legislation to limit what recipients of the Supplemental Nutrition Assistance Program can...
WATCH: Congressional seat at stake; Pritzker on Medicaid costs, school choice, ICE

WATCH: Congressional seat at stake; Pritzker on Medicaid costs, school choice, ICE

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop continues to unpack data...
Illinois Quick Hits: Man charged with threatening ICE agents

Illinois Quick Hits: Man charged with threatening ICE agents

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – An Illinois man is charged with threatening to kill federal agents working for U.S. Immigration and Customs...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board for January 15, 2026

Will County Board Meeting | January 15, 2026 Meeting SummaryThe Will County Board met on January 15, 2026, to tackle a heavy agenda focused on infrastructure investment, legislative policy, and...
Remote marriage license bill faces skepticism from former clerk

Remote marriage license bill faces skepticism from former clerk

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – A new Illinois proposal aimed at expanding access to marriage licenses for people with disabilities or...
Lawsuit: Illinois Dems can’t use state law to control the name ‘democrat’

Lawsuit: Illinois Dems can’t use state law to control the name ‘democrat’

By Jonathan Bilyk | Legal NewslineThe Center Square A group of Illinois Democrats who disagree with the power structure of their party on how to address transgender civil rights law...
Police Crime

Pursuit following railroad theft ends in New Lenox; one suspect at large

NEW LENOX, Ill. – A reported cargo theft in Wilmington Township sparked a multi-jurisdictional pursuit Saturday morning that ended with a crash and a manhunt in a New Lenox neighborhood. The...
Will County Board Graphic.04

Waste Management Commits to Expanded Litter Patrols Around Landfill

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Following complaints from county officials, Waste Management has agreed to significantly expand its litter collection efforts along roadways surrounding...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for Jan. 13, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, January 13, 2026, to continue its comprehensive update...
Fire EMS Traffic Collission

Traffic Crash Closes Wilmington-Peotone Road Near Manhattan

Update: At approximately 5:54 this morning, January 27/2026, there was a two-vehicle crash involving a car and a tractor trailer near 104th Avenue and Wilmington-Peotone Road. The roadway remains shut...
Will County Board Graphic.01

County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved major infrastructure contracts, including an $18.8 million bridge replacement on Lorenzo Road and a $3.2...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for Dec. 15, 2025

Manhattan Fire Protection District Meeting | Dec. 15, 2025 The Manhattan Fire Protection District Board of Trustees met on Monday, Dec. 15, to handle end-of-year business, including insurance renewals, contract...
Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable...