Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Manhattan Weather Full forecast →
Sat Jun 6
Slight Chance Showers And Thunderstorms then Chance Showers And Thunderstorms
83° 68°

Slight Chance Showers And Thunderstorms then Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 55%

Leave a Comment





Latest News Stories

WATCH: GOP governor candidates forum highlights; Pritzker talks taxes increase, Bears

WATCH: GOP governor candidates forum highlights; Pritzker talks taxes increase, Bears

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop provides highlights from Monday...
Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – As Illinois lawmakers convene for the 2026 legislative session, House Bill 3320, Responsibility in Firearm Legislation...
SCOTUS declines to hear felony firearms cases

SCOTUS declines to hear felony firearms cases

By Andrew RiceThe Center Square The U.S. Supreme Court on Tuesday declined to take up two cases over whether individuals with felony records can be permanently disarmed under the Second...
Illinois Quick Hits: No injuries reported in Tuesday earthquake

Illinois Quick Hits: No injuries reported in Tuesday earthquake

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – No injuries have been reported after the U.S. Geological Survey reported a magnitude 3.8 earthquake near the...
One year in: Reviewing Trump's inaugural promises

One year in: Reviewing Trump’s inaugural promises

By Andrew RiceThe Center Square One year ago Tuesday, President Donald Trump told the nation its “golden age” had arrived, promising to spend his second term restoring stability at home...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way Plans New Turf Field at Central and Courts at West for 2026

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: District 210 administrators presented a $4.5 million capital projects plan for Summer 2026, headlined by a new auxiliary...
Will County Board Graphic.04

Frankfort Township Road Commissioner Warns County Panel Against Low-Speed Vehicles

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee moved forward with a ban on low-speed vehicles on...
GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – All four Illinois Republican gubernatorial candidates have no shortage of criticism for current Gov. J.B. Pritzker. 2022...
Illinois lawmaker questions IDHS over years-long data breach

Illinois lawmaker questions IDHS over years-long data breach

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – An Illinois lawmaker slammed the state agency as “incompetent” after the Department of Human Services revealed...
Will County Board Graphic.04

Draft County Federal Agenda Opposes Sharing Medicaid Patient Data with ICE

Article Summary: A proposed federal policy platform presented to the Will County Board takes a hard line against a federal agreement that allows Immigration and Customs Enforcement (ICE) to access...
Will County Logo Graphic

Northern Builders Development Brings Changes to Laraway and Gougar Roads in New Lenox

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved access permits for a new development by Northern Builders at the intersection of Laraway Road...
Manhattan School District 114 Logo Graphic

Manhattan 114 Approves Insurance Renewal Amidst Cost Increases

Manhattan School District 114 Meeting | Jan. 14, 2026 Article Summary: The Manhattan School District approved a renewal of its comprehensive insurance package despite a substantial increase in premiums. The...

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for January 6, 2026

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Public Works & Transportation Committee met on Tuesday, January 6, 2026, to discuss...
Will County Board Graphic.03

County Board Debates Legislative Agendas; State Agenda Passes, Federal Agenda Sent Back

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board engaged in a vigorous and at times confusing debate over its 2026 legislative priorities, ultimately passing...
lincoln way school district 210 logo.1

District 210 Updates Online Course Policy and Increases Summer School Fees

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: The Board of Education approved an increase in summer school fees and clarified policies regarding online coursework for...