will county board meeting graphic.5

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for April 7, 2026

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

The Will County Board Public Works & Transportation Committee met on Tuesday, April 7, 2026, moving forward a massive slate of infrastructure contracts totaling nearly $10 million. Beyond the high-profile speed limit debates on Cedar Road and the initiation of the Bluff Road reconstruction, the committee swiftly approved a series of construction awards and Phase II design contracts to prep the county for the summer building season. Assistant County Engineer Brian Gizki reported that pre-construction meetings are already being scheduled, with asphalt plants expected to open by early April.

Francis Road Construction Awarded: The committee confirmed the award of a $2,984,218.25 contract to Austin Tyler Construction, Inc. for the reconstruction and widening of Francis Road (CH 64). The project, which spans from Gougar Road (CH 52) to I-80, includes storm sewer installation, drainage ditch improvements, and retaining wall construction. During construction, the roadway will be closed to through traffic.

Plainfield Township and Renwick Road Resurfacing: P.T. Ferro Construction Co. secured two major resurfacing contracts. The first, a $958,266.60 contract, covers Renwick Road (CH 36) from east of U.S. Route 30 to west of Weber Road. The second, a $194,014.90 contract, covers various Plainfield Township roadways, including Williamsburg Drive, Jamestown Road, and Virginia Drive. Both projects are slated to begin in June 2026.

Traffic Signal System Upgrades: The committee approved a $140,783.00 Phase II design agreement with AECOM Technical Services, Inc. to modernize traffic signals and incorporate them into the county’s Centralized Traffic Signal System (CTSS) via fiber optic cable. The upgrades cover 14 intersections across Plainfield-Naperville Road, Briggs Street, Francis Road, Laraway Road, and 191st Street, and include the installation of 13 pan/tilt/zoom traffic cameras.

Laraway Road Right-of-Way Acquisition: To prepare for the future widening of Laraway Road (CH 74) at U.S. Route 45, the committee appropriated $1,409,940.00 in transportation funds to acquire necessary right-of-way. The funds authorize the county to negotiate with property owners or, if necessary, utilize eminent domain to secure the land required for new turn lanes and traffic signals.

Bridge Maintenance Design Contract: Willett, Hofmann & Associates was awarded a $227,361.00 Phase II design contract to engineer maintenance and repair work for 12 various county highway bridges. The targeted structures span multiple county board districts and include crossings over the Des Plaines River, Prairie Creek, Plum Creek, and the South Branch of Forked Creek.

Leave a Comment





Latest News Stories

New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...
Meeting Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
Fire-Accident-Emergency-Graphic.3

Fatal Crash, Second Collision Snarl Wilmington-Peotone Road

A fatal crash on Wilmington-Peotone Road Tuesday morning was complicated by a second, separate collision in the same area, prompting an extended closure of the roadway as emergency crews work...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for June 2025

Manhattan Township Meeting | June 2025 The Manhattan Township Board passed its two largest annual fiscal items on Tuesday, June 10, 2025, unanimously approving township and road district budgets that...
Manhattan Township

Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete

Manhattan Township Meeting | June 2025 Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...