Will County Public Works & Transportation Committee Meeting | April 7, 2026
The Will County Board Public Works & Transportation Committee met on Tuesday, April 7, 2026, moving forward a massive slate of infrastructure contracts totaling nearly $10 million. Beyond the high-profile speed limit debates on Cedar Road and the initiation of the Bluff Road reconstruction, the committee swiftly approved a series of construction awards and Phase II design contracts to prep the county for the summer building season. Assistant County Engineer Brian Gizki reported that pre-construction meetings are already being scheduled, with asphalt plants expected to open by early April.
Francis Road Construction Awarded: The committee confirmed the award of a $2,984,218.25 contract to Austin Tyler Construction, Inc. for the reconstruction and widening of Francis Road (CH 64). The project, which spans from Gougar Road (CH 52) to I-80, includes storm sewer installation, drainage ditch improvements, and retaining wall construction. During construction, the roadway will be closed to through traffic.
Plainfield Township and Renwick Road Resurfacing: P.T. Ferro Construction Co. secured two major resurfacing contracts. The first, a $958,266.60 contract, covers Renwick Road (CH 36) from east of U.S. Route 30 to west of Weber Road. The second, a $194,014.90 contract, covers various Plainfield Township roadways, including Williamsburg Drive, Jamestown Road, and Virginia Drive. Both projects are slated to begin in June 2026.
Traffic Signal System Upgrades: The committee approved a $140,783.00 Phase II design agreement with AECOM Technical Services, Inc. to modernize traffic signals and incorporate them into the county’s Centralized Traffic Signal System (CTSS) via fiber optic cable. The upgrades cover 14 intersections across Plainfield-Naperville Road, Briggs Street, Francis Road, Laraway Road, and 191st Street, and include the installation of 13 pan/tilt/zoom traffic cameras.
Laraway Road Right-of-Way Acquisition: To prepare for the future widening of Laraway Road (CH 74) at U.S. Route 45, the committee appropriated $1,409,940.00 in transportation funds to acquire necessary right-of-way. The funds authorize the county to negotiate with property owners or, if necessary, utilize eminent domain to secure the land required for new turn lanes and traffic signals.
Bridge Maintenance Design Contract: Willett, Hofmann & Associates was awarded a $227,361.00 Phase II design contract to engineer maintenance and repair work for 12 various county highway bridges. The targeted structures span multiple county board districts and include crossings over the Des Plaines River, Prairie Creek, Plum Creek, and the South Branch of Forked Creek.
Latest News Stories
Health & Safety Committee: Opioid Overdose Deaths Drop to Zero in January as Behavioral Health Department Expands Role
State of the College: JJC Announces Plans for New Campus in Grundy County
Meeting Summary and Briefs: Manhattan Village Board for Feb. 3, 2026
Meeting Summary and Briefs: Public Works & Transportation Committee for February 3, 2026
Health & Safety Committee: District 3 Board Member Pushes for Expanded Animal Control Services in Monee, Crete
Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for Jan. 6, 2026
Legislative Committee: Lobbyists Report on Federal Shutdown and Legislative Outlook
County Authorizes Financial Study of Homer Glen Law Enforcement Contract
Meeting Summary and Briefs: Joliet Junior College Board of Trustees Workshop for January 28, 2026
IDOT Implementing Speed Limit Changes in Manhattan
Will County Public Works Debates Future Bridge Needs as 159th Street Closure Looms
Capital Imp Committee: Veterans Assistance Commission Set to Move into New Facility