Will County Planning and Zoning Commission Meeting | April 7, 2026

Article Summary: The Will County Planning and Zoning Commission voted to overturn administrative denials for two delayed commercial projects—a rural wedding venue in Joliet and a petroleum barge terminal in Romeoville—after applicants missed strict deadlines to file for special use permit extensions.

Zoning Appeals Key Points:

  • Rosalio Acosta Enterprises won Appeal #AA-26-001 after missing a February 13 deadline by 12 days for a special use permit extension for a Joliet wedding barn on Baltz Road.

  • The Metropolitan Water Reclamation District (MWRD) and Ducere LLC won Appeal #AA-26-002 after missing a January 15 deadline for a barge transloading facility on the Chicago Sanitary & Ship Canal in Romeoville.

  • County zoning code forces the Zoning Administrator to automatically reject late extension requests, requiring applicants to appeal to the Commission and claim the staff made an “error” to keep their permits alive.

  • Commissioners voiced frustration with the required legal wording of the appeals, noting that staff did not actually make a mistake by following the ordinance.

On Tuesday, April 7, 2026, the Will County Planning and Zoning Commission utilized the administrative appeal process to rescue two major commercial developments from bureaucratic death, voting to override staff rejections caused by missed paperwork deadlines.

The commission heard two back-to-back appeals: Appeal #AA-26-001 for Rosalio Acosta Enterprises LTD regarding a property at 26228 W. Baltz Road in Troy Township, and Appeal #AA-26-002 for the Metropolitan Water Reclamation District (MWRD) and Ducere LLC regarding a 39-acre parcel at 18500 W. 9th Street in Romeoville.

In both cases, the applicants had previously received Special Use Permits (SUPs) from the Will County Board that required periodic extensions while they worked through complex building and site development permitting. And in both cases, the applicants filed their extension paperwork after the expiration dates.

Development Services Director Brian Radner explained that the zoning ordinance explicitly states that extension requests must be submitted before the special use permit expires.

For the Acosta property, which is developing a wedding barn with ancillary liquor service, the previous extension expired on February 13, 2026. The applicant submitted the new request 12 days later, on February 25. For the Ducere LLC barge terminal—a facility designed to transfer petroleum products from pipelines to barges—the permit expired on January 15, 2026. The applicant’s agent, Dave Nelson, submitted the extension on February 25, having mistakenly calculated the deadline from the date of his previous county board meeting.

Because the deadlines were missed, the Zoning Administrator was legally forced to reject the applications. The only recourse for the applicants to avoid starting the expensive and time-consuming SUP process completely over from scratch was to appeal to the Planning and Zoning Commission.

“They’d like the Planning and Zoning Commission to decide if we made the correct decision, and if you want to overrule staff’s decision,” Radner explained to the commissioners. “The implication of not siding with the applicant would mean that they’d have to go through the special use permit process again.”

To grant the applicants relief, the commission had to pass a motion explicitly stating that the “administrative decision being appealed is an error.”

This legal phrasing drew significant irritation from the commissioners, who universally agreed that Radner and his staff had followed the law perfectly and made no actual error.

“I think that something needs to be changed about the way these cases are worded,” Commissioner Kimberly Mitchell stated during the vote. “I mean there needs to be another way that we can approve but not say that staff is wrong.”

Chairman Hugh Stipan echoed the frustration, noting, “It is painful to say that staff made a mistake when they really didn’t make a mistake, and that’s the way we got it worded.”

Despite the semantic objections, the commission voted 4-1 to approve the Acosta appeal, and 5-0 to approve the MWRD/Ducere appeal. The affirmative votes mandate the Zoning Administrator to accept the late extension applications, which will now be forwarded to the Will County Board’s Land Use and Development Committee for final approval.

Manhattan Weather Full forecast →
Today Jun 3
Mostly Sunny
86° 65°

Mostly Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
MH VB 6-3

Village Releases $2.8 Million Letter of Credit for Completed Stonegate Subdivision

The Manhattan Village Board approved the release of a nearly $2.9 million letter of credit for the Stonegate subdivision after village engineers confirmed all required public improvements have been completed....
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...