Millions Approved for Will County Highway and Road Infrastructure Projects
Will County Board Meeting | April 16, 2026
Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road, and Laraway Road.
Infrastructure Key Points:
-
Austin Tyler Construction was awarded a $2,984,218.25 contract to rebuild and widen Francis Road.
-
P.T. Ferro Construction secured a $958,266.60 contract to resurface Renwick Road.
The Will County Board on Thursday, April 16, 2026, greenlit a slate of major infrastructure investments across the region, passing multiple resolutions on the consent agenda without opposition.
The largest expenditure was authorized by Resolution 26-113, which awarded a $2,984,218.25 contract to Austin Tyler Construction, Inc. The Elwood-based firm was the low bidder for a comprehensive project on Francis Road (County Highway 64) from Gougar Road to Wirt Road in County Board District 5. The scope of work includes roadway reconstruction and widening, storm sewer installation, drainage ditch improvements, culvert reconstruction, and retaining wall installation. The project is slated to begin in June 2026, during which the road will be closed to through traffic.
In Plainfield Township, the Board approved Resolution 26-114, confirming a $958,266.60 contract with Joliet-based P.T. Ferro Construction Co. The firm will resurface Renwick Road (CH 36) from east of U.S. Route 30 to west of Weber Road. The project, which also begins in June, will utilize Hot-Mix Asphalt (HMA) surface removal and replacement, centerline rumble strips, and deck slab repairs. The roadway will remain open during construction with periodic lane closures guided by flaggers. P.T. Ferro also secured a separate $194,014.90 contract (RES 26-115) to resurface various subdivision roadways within the Plainfield Road District.
The Board also took action on Laraway Road in New Lenox. Resolution 26-112 authorizes an agreement with LNS Development Group, LLC for stormwater management improvements along Laraway Road between Cedar Road and Spencer Road. The county will reimburse the developer an estimated $352,071.95 for the construction of a shared detention facility and storm sewer upgrades required for the county’s future plans to widen Laraway to a four-lane, barrier-median roadway.
Latest News Stories
WATCH: Pritzker encourages protests as feds challenge use of force lawsuit
Attorneys general oppose pay cut for foreign farmworkers
WATCH: Pritzker signs vaccine law GOP doctor called ‘Trump Derangement’ bill
Illinois, Chicago residents rank high taxes as state’s top issue
Illinois quick hits: Biss criticizes university payout; more time in emergency rooms
WATCH: Sanctuary bill soon law; Use of force case proceeds; CTU audits due Mon
Park District Board Approves New Management Job Descriptions
CTU can’t sue group for campaigning in union elections
IL U.S. House candidate: drug screen expectant moms getting subsidies
Illinois quick hits: Ameren requests rate hike; Pearl Harbor remembrance
First Look at Lincoln-Way 210’s Proposed 2026-2027 School Calendar
Meeting Summary and Briefs: Manhattan Township Board for October 2025