Will County Board Graphic.01

Millions Approved for Will County Highway and Road Infrastructure Projects

Spread the love

Will County Board Meeting | April 16, 2026

Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road, and Laraway Road.

Infrastructure Key Points:

  • Austin Tyler Construction was awarded a $2,984,218.25 contract to rebuild and widen Francis Road.

  • P.T. Ferro Construction secured a $958,266.60 contract to resurface Renwick Road.

The Will County Board on Thursday, April 16, 2026, greenlit a slate of major infrastructure investments across the region, passing multiple resolutions on the consent agenda without opposition.

The largest expenditure was authorized by Resolution 26-113, which awarded a $2,984,218.25 contract to Austin Tyler Construction, Inc. The Elwood-based firm was the low bidder for a comprehensive project on Francis Road (County Highway 64) from Gougar Road to Wirt Road in County Board District 5. The scope of work includes roadway reconstruction and widening, storm sewer installation, drainage ditch improvements, culvert reconstruction, and retaining wall installation. The project is slated to begin in June 2026, during which the road will be closed to through traffic.

In Plainfield Township, the Board approved Resolution 26-114, confirming a $958,266.60 contract with Joliet-based P.T. Ferro Construction Co. The firm will resurface Renwick Road (CH 36) from east of U.S. Route 30 to west of Weber Road. The project, which also begins in June, will utilize Hot-Mix Asphalt (HMA) surface removal and replacement, centerline rumble strips, and deck slab repairs. The roadway will remain open during construction with periodic lane closures guided by flaggers. P.T. Ferro also secured a separate $194,014.90 contract (RES 26-115) to resurface various subdivision roadways within the Plainfield Road District.

The Board also took action on Laraway Road in New Lenox. Resolution 26-112 authorizes an agreement with LNS Development Group, LLC for stormwater management improvements along Laraway Road between Cedar Road and Spencer Road. The county will reimburse the developer an estimated $352,071.95 for the construction of a shared detention facility and storm sewer upgrades required for the county’s future plans to widen Laraway to a four-lane, barrier-median roadway.

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
Meeting Briefs

Meeting Summary and Briefs: Jackson Township Board for August 13, 2025

The Jackson Township Board took the next step in reviewing a proposed anaerobic digester project at its meeting on Wednesday, August 13, 2025, referring the plan from Elwood81, LLC, to...
Jackson Township

Jackson Township to Investigate Decade-Old High-Speed Rail Plan Through Elwood

Article Summary: Jackson Township officials are seeking information on a high-speed rail plan dating back to 2012 that would route a passenger line through the Elwood area. Supervisor Matt Robbins...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for August 14, 2025

The Manhattan Park Board made significant progress on its flagship Round Barn Farm project during its meeting on August 14, 2025. Commissioners unanimously approved hiring a new architect, Arete Design...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
jackson township graphic.1

Jackson Township Approves Settlement with Joliet, Union Pacific Over ICC Case

Article Summary: The Jackson Township Board unanimously approved a settlement agreement involving the City of Joliet and Union Pacific Railroad, formally resolving a multi-year case before the Illinois Commerce Commission....
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
manhattan park district graphic.1

Manhattan Park Board Deadlocks on Paying for Sports Complex Plan, Motion Fails

Article Summary: A proposal for the Manhattan Park District to fund an architectural concept plan for a new sports complex failed to pass on Thursday, August 14, 2025, after a...
manhattan elwood library graphic.5

Manhattan-Elwood Library Board Adopts Annual Budget and Appropriation Ordinance

Article Summary: The Manhattan-Elwood Public Library District Board of Trustees has formally adopted its budget for the upcoming fiscal year following a public hearing. The approval of the combined Budget...