Manhattan School District 114 Board of Education Meeting | April 29, 2026

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a summer roofing repair contract for three of its school buildings and outlined an extensive capital projects schedule. The work includes roofing, seal coating, Phase 2 LED lighting upgrades, and preparation for a major HVAC overhaul at Anna McDonald and Manhattan Intermediate School.

Capital Projects Key Points:

  • Roofing repairs will span from June 9 to August 12 across Wilson Creek, Anna McDonald, and MIS.

  • The district added a $50,000 to $60,000 shingle replacement at Wilson Creek based on architectural audits.

  • The modular classrooms at Wilson Creek will be removed the week of June 20.

  • A $19,000 seal coating project is slated for Wilson Creek in late July.

The Manhattan School District 114 Board of Education on Tuesday, April 29, 2026, unanimously approved an independent contractor agreement to execute comprehensive roof repairs across Wilson Creek Elementary, Anna McDonald School, and Manhattan Intermediate School (MIS).

The roofing project, coordinated between STR Partners and Anthony Roofing, is scheduled to commence on June 9, the first week after students are dismissed for the summer. Crews will start at Wilson Creek, move to Anna McDonald, and finish at MIS, dedicating roughly three to four weeks to each building. The target completion date is August 12, roughly a week before the new school year begins.

Administrators confirmed that the approved contract includes an added scope of work for Wilson Creek. Based on a 10-year facility audit conducted by STR, the district opted to replace the building’s shingles for an estimated $50,000 to $60,000 while crews are already mobilized on-site.

“Considering we’re doing everything else, it would be kind of silly to come back and do that,” Board President John Burke said before the 5-0 roll call vote.

The roofing contract is just one piece of a packed summer capital improvement schedule. District facilities staff updated the Board on several imminent upgrades, including a $19,000 seal coating project at Wilson Creek scheduled for the week of July 20, which will require subsequent Board approval due to the bidding threshold.

Inside Wilson Creek, district custodians are currently working to paint classrooms for the first time in 20 years. Priority is being given to the rooms designated for the Preschool for All (PFA) program. The PFA classes will be moving out of the temporary modular classrooms, which are scheduled to be physically removed from the campus the week of June 20.

The Board also reviewed plans to stagger Phase 2 of the district’s lighting upgrades to avoid triggering legal bidding thresholds. The district plans to approve lighting for MIS in May, Anna McDonald in June, and break Wilson Creek’s lighting into two parts spanning July and August. Administrators noted Phase 3 will likely target the district’s dim bathroom spaces.

Looking ahead, the district is preparing for its most expensive upcoming capital project: a full HVAC replacement at Anna McDonald and MIS. STR Partners and 2010 Engineering are currently developing the scope of work based on a recent facility walkthrough.

When Board Member Erica Aultz asked what season HVAC repairs generally occur, staff confirmed the work is strictly relegated to the summer months due to the highly intrusive nature of ripping out unit ventilators and potentially updating the boiler systems. The district expects to put the HVAC project out to bid in the fall to lock in pricing for next year.

Leave a Comment





Latest News Stories

MH 114 SB July 9, 2025

Manhattan 114 Board Hires New Teachers, Accepts Staff Resignations

The Manhattan School District 114 Board of Education approved the hiring of four certified teachers and three non-certified staff members for the upcoming school year during its meeting on July...
MH 114 SB July 9, 2025

District 114 Approves Federal Plan as Construction Nears Finish Line

The Manhattan School District 114 Board of Education took a key step in securing federal funding for the next fiscal year and received positive updates on the final stages of...
Meeting Briefs

Meeting Briefs: Manhattan School District 114 for July 9, 2025

Junior High Announces Mascot Debut, Community Events: Manhattan Junior High School is preparing to introduce its new mascot, “Demo,” at the PTO’s Back to School Bash on August 15 from 5:00...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...
Will-County-Land-Use-July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department May Seek Property Tax Increase to Maintain Critical Services

The Will County Health Department is grappling with significant budget shortfalls as multiple federal grants have been terminated or reduced, potentially forcing the agency to seek additional property tax revenue...
Will-County-Land-Use-July-3.1

Crete Township Solar Project Approved Despite Township Objections

A 21-acre commercial solar project in Crete Township received a favorable recommendation from the Will County Land Use and Development Committee on Thursday, despite an official objection from the township....
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Opens Second Breast Milk Depot in Bolingbrook

The Will County Health Department has opened its second breast milk depot in partnership with Mother's Milk Bank of the Western Great Lakes, expanding access to donated breast milk for...
Will-County-Land-Use-July3.2

Lockport Township Solar Farm Gains Committee Approval

The Will County Land Use and Development Committee on Thursday approved a special use permit for a 25-acre commercial solar energy facility in Lockport Township. The project, proposed by Daniel...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Plans Back-to-School Fair July 12

The Will County Health Department will host a Back-to-School Health Fair Saturday, July 12, from 10 a.m. to 2 p.m. at the Community Health Center, 1106 Neal Ave., Joliet. The...
Meeting Briefs

Meeting Briefs: Will County Land Use & Development Committee for July 3, 2025

Green Garden Township Rezoning for Future Subdivision ApprovedThe committee recommended approval of a map amendment for an 81-acre property on South 88th Avenue in Green Garden Township. The applicant, represented...
Meeting Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
MH VB 7-1

Manhattan awards $1.9M contract for Eastern Avenue rebuild

The Village of Manhattan Board approved a $1.94 million contract with PT Ferrell Construction for the reconstruction of Eastern Avenue from North Street to Smith Road during their July 1...