Manhattan School District 114 Board of Education Meeting | April 29, 2026

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a summer roofing repair contract for three of its school buildings and outlined an extensive capital projects schedule. The work includes roofing, seal coating, Phase 2 LED lighting upgrades, and preparation for a major HVAC overhaul at Anna McDonald and Manhattan Intermediate School.

Capital Projects Key Points:

  • Roofing repairs will span from June 9 to August 12 across Wilson Creek, Anna McDonald, and MIS.

  • The district added a $50,000 to $60,000 shingle replacement at Wilson Creek based on architectural audits.

  • The modular classrooms at Wilson Creek will be removed the week of June 20.

  • A $19,000 seal coating project is slated for Wilson Creek in late July.

The Manhattan School District 114 Board of Education on Tuesday, April 29, 2026, unanimously approved an independent contractor agreement to execute comprehensive roof repairs across Wilson Creek Elementary, Anna McDonald School, and Manhattan Intermediate School (MIS).

The roofing project, coordinated between STR Partners and Anthony Roofing, is scheduled to commence on June 9, the first week after students are dismissed for the summer. Crews will start at Wilson Creek, move to Anna McDonald, and finish at MIS, dedicating roughly three to four weeks to each building. The target completion date is August 12, roughly a week before the new school year begins.

Administrators confirmed that the approved contract includes an added scope of work for Wilson Creek. Based on a 10-year facility audit conducted by STR, the district opted to replace the building’s shingles for an estimated $50,000 to $60,000 while crews are already mobilized on-site.

“Considering we’re doing everything else, it would be kind of silly to come back and do that,” Board President John Burke said before the 5-0 roll call vote.

The roofing contract is just one piece of a packed summer capital improvement schedule. District facilities staff updated the Board on several imminent upgrades, including a $19,000 seal coating project at Wilson Creek scheduled for the week of July 20, which will require subsequent Board approval due to the bidding threshold.

Inside Wilson Creek, district custodians are currently working to paint classrooms for the first time in 20 years. Priority is being given to the rooms designated for the Preschool for All (PFA) program. The PFA classes will be moving out of the temporary modular classrooms, which are scheduled to be physically removed from the campus the week of June 20.

The Board also reviewed plans to stagger Phase 2 of the district’s lighting upgrades to avoid triggering legal bidding thresholds. The district plans to approve lighting for MIS in May, Anna McDonald in June, and break Wilson Creek’s lighting into two parts spanning July and August. Administrators noted Phase 3 will likely target the district’s dim bathroom spaces.

Looking ahead, the district is preparing for its most expensive upcoming capital project: a full HVAC replacement at Anna McDonald and MIS. STR Partners and 2010 Engineering are currently developing the scope of work based on a recent facility walkthrough.

When Board Member Erica Aultz asked what season HVAC repairs generally occur, staff confirmed the work is strictly relegated to the summer months due to the highly intrusive nature of ripping out unit ventilators and potentially updating the boiler systems. The district expects to put the HVAC project out to bid in the fall to lock in pricing for next year.

Leave a Comment





Latest News Stories

Village of Manhattan Logo Graphic

Manhattan Honors Departing Officials at Final Board Meeting

Beemsterboer, Adamski and Lewis recognized for combined 32 years of public service The Village of Manhattan honored three departing officials Tuesday evening, recognizing their combined 32 years of public service...
Village of Manhattan Logo Graphic

Manhattan Village Board Meeting Briefs

New Police Vehicles Approved: The village board authorized purchasing two new police interceptors for $157,362 total. A 2025 Ford F-150 will replace squad 773 for truck enforcement duties, while a...
MFPD-Logo-Fire District

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire District

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire District

Fire District May 21 Meeting Briefs

Policy Manual Nearly Complete: The district's operational procedures and policy manual is 95% complete, with attorney review and union input ongoing. The complete manual will be presented to the board...
lincoln way school district

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln way school district

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln way school district.3

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...
Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...