Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township
Will County Planning and Zoning Commission Meeting | May 5, 2026
Article Summary: The Will County Planning and Zoning Commission on May 5, 2026, unanimously approved two major public utility requests and associated fence variances to facilitate the construction of regional water storage and pumping facilities. The 40-acre development at Black Road and County Line Road is a critical component of a $1.446 billion initiative to deliver Lake Michigan water to six Will County municipalities by 2030.
Water Infrastructure Key Points:
-
Project Scope: The development includes a 1.5 million-gallon “spheroid” elevated storage tank standing 145 feet tall, a pump station, and a public works garage.
-
Dual Ownership: The site is divided into two 20-acre parcels—one owned by the Grand Prairie Water Commission (ZC-26-019) and one by the City of Joliet (ZC-26-018).
-
Regional Impact: The facilities will serve 250,000 residents across Joliet, Shorewood, Crest Hill, Channahon, Minooka, and Romeoville.
-
Security Measures: Both parcels were granted variances to install 8-foot-tall security fences (7-foot chain link with 1 foot of barbed wire), exceeding the standard 7-foot limit for the A-1 district.
JOLIET — A massive regional effort to secure a sustainable water supply for Will County took a significant step forward Tuesday, May 5, 2026, as the Planning and Zoning Commission cleared the way for the Grand Prairie Water Commission (GPWC) and the City of Joliet to begin developing a critical infrastructure hub in Troy Township.
The two related cases, ZC-26-018 and ZC-26-019, involve adjacent vacant properties located at the southeast corner of Black Road and County Line Road. The project is born of necessity; Allison Swisher, Director of Public Utilities for Joliet, testified that the region’s existing deep aquifer is failing and will be unable to meet maximum demand by 2030.
“We selectioned purchasing water from the City of Chicago as the most sustainable and reliable option,” Swisher told the commission. “The majority of this project will serve Will County residents.”
Site Specifics and Security
The GPWC parcel (ZC-26-019) will house the project’s second intermediate storage facility, featuring a 1.5 million-gallon steel tank. The City of Joliet’s neighboring parcel (ZC-26-018) will include additional water storage tanks, a public works garage, and an outdoor storage yard.
Because of the “critical” nature of the water supply, the applicants requested variances to allow for 8-foot-tall fencing topped with barbed wire for security. Staff recommended approval, noting that while the area remains primarily agricultural, it is slated for future residential growth that requires this infrastructure.
Commissioner John Kiefner questioned why the properties were not being annexed into Joliet. Swisher responded that while annexation is likely in the future, the commission needs to begin construction immediately to meet the 2030 deadline for water delivery.
The commission approved the Special Use Permits and the fence variances for both parcels without a single dissenting vote.
Latest News Stories
States challenge federal report promoting coal plants
U.S. Supreme Court could rule on Texas lawsuits brought in Democratic-led state courts
WATCH: Illinois In Focus Daily | Monday Aug. 11th, 2025
Illinois quick hits: Judge denies Madigan’s motion; legislator urges action on DCFS interns
About Us
Everyday Economics: CPI takes center stage as tariff-driven price pressures mount
Net negative migration is harmful to the economy, economists say
Details pending on billions in foreign investments coming from trade deals
Will County Health Department Seeks $1 Million to Avert ‘Drastic’ Service Cuts from Expiring Grants
Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate
Improved Vendor Service Creates $1.2 Million Shortfall in Sheriff’s Medical Budget
Will County Public Works Committee Unveils 25-Year Transportation Plan, Projects $258 Million Gap
Will County Animal Protection Services Seeks New Facility Amid “Gaping Wound” of Space Crisis