Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus

Spread the love

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026

Article Summary
The Will County Capital Improvements & IT Committee is evaluating four multi-million-dollar proposals to replace aging county buildings, balancing the specific spatial needs of the County Clerk’s office with a debate over the legalities and logistics of potentially relocating the county seat.

Will County Master Plan Key Points:

  • Wight & Company presented four building consolidation options ranging in cost from $239 million to over $306 million.

  • County Clerk Kimberly Fladhammer and her staff requested 20,000 to 40,000 square feet of dedicated warehouse space for election equipment, which is not fully addressed in current proposals.

  • Board Member Steve Balich (R-Homer Glen) suggested moving county operations to a “green space” campus outside Joliet to solve parking and expansion issues.

  • The State’s Attorney’s office confirmed that moving the county seat from Joliet requires a county-wide voter referendum.

The Will County Board Capital Improvements & IT Committee on Tuesday, May 5, 2026, reviewed four extensive architectural proposals from Wight & Company to consolidate and replace aging county facilities, sparking a complex debate over space, cost, and location.

With the current County Office Building and the EMCO building requiring significant ongoing maintenance, the county is exploring a massive infrastructure overhaul. Mike Mahoney from the County Executive’s office presented the four options, which all hover around the $300 million mark.

Option 1 proposes two separate county buildings—one for auxiliary court functions (State’s Attorney and Public Defender) with a parking garage, and a new County Office Building at the site of the old courthouse. The estimated cost ranges from $239,030,000 to $302,030,000.

Option 2 features a partnership with the City of Joliet, combining city and county offices into one complex, with an estimated total cost between $239,550,000 and $303,730,000, though Joliet would cover the costs of its own square footage. Options 3 and 4 present variations of these configurations, with Option 4 encompassing a massive 385,600 gross square-foot building housing Judicial Agency Offices, the County Office, and the City of Joliet, plus a 230,400 square-foot parking garage, topping out at an estimated $306,040,000.

“Both buildings that we’re in right now for the State’s Attorney and probation… and the EMCO building, that building is in, I don’t want to say a state of disrepair, but it is very old,” Mahoney told the committee. “There are wood floors still throughout, wood subflooring throughout. It needs a lot of work to keep maintaining, and it will continue to cost the county additional millions of dollars in maintenance costs over the next five to 10 years. Obviously, the same with this building [the current County Office Building].”

The logistical challenge of the master plan was highlighted by the Will County Clerk’s Office. County Clerk Kimberly Fladhammer and her Chief of Staff addressed the committee regarding critical space shortages affecting election operations.

The Clerk’s office currently operates with approximately 4,000 square feet in the basement to house election day equipment and cages. They noted that comparable counties utilize warehouses ranging from 20,000 to 40,000 square feet. Furthermore, the office requires dedicated space for election judge training—currently held in a borrowed Human Resources conference room—and a secure event space for central and provisional ballot counting.

“The proposal by White was approximately 33,000 square feet for the county clerk’s office, which I think would be sufficient for the day-to-day operational issues with vital records,” the Clerk’s Chief of Staff said. However, she noted it would not satisfy the massive warehouse need for equipment, which requires specialized logistical access like freight elevators and loading docks.

Board Member Steve Balich (R-Homer Glen) argued that the spatial constraints and parking issues in downtown Joliet justify moving the county’s operations entirely.

“Most of the people on the board back in the day before the courthouse was built wanted to create a green space and build our own campus, and that would eliminate all the problems going forward,” Balich said. “There’s a whole lot of land in Joliet when you go west close to Grundy County like by Minooka… There’s a whole lot of land where they want to put big solar farms in Manhattan.”

However, relocating the core functions of the county government faces a strict legal hurdle. An Assistant State’s Attorney present at the meeting clarified the statutory limitations.

“The county seat is Joliet,” the attorney stated. “You need a referendum of the whole county to move the county seat. You could move it if everybody agreed in the county that voted for it… but we cannot move the county seat just by county board action.”

Board Member Jacqueline Traynere (D-Bolingbrook), attending the meeting as a guest, reminded the committee of the historical context behind keeping the campus downtown.

“The cost to move people that are housed in the jail to a courthouse that would be built on a green space in New Lenox was just not going to be supported,” Traynere said. “Not only the cost, but just the security issues. So that was the main reason why we chose to go forward with the courthouse downtown as opposed to a green space.”

The committee did not take a formal vote on the options. Instead, members requested that Wight & Company provide additional configurations, including assessing the feasibility of adding floors to the current County Office Building—a 1949 structure originally built as a Sears store—and exploring development on the north end of the current parking lot.

Leave a Comment





Latest News Stories

WCO-PZ-Aug-5.2

Homer Glenn Residents Push Back on 143rd Street Widening as Officials Signal “Tentative Agreement”

ARTICLE SUMMARY: A Homer Glenn farm owner voiced strong opposition to the planned widening of 143rd Street during a county meeting, while committee members indicated a "tentative agreement" is in the...
WCO-LEG-8.5.1

Will County Forges 2026 Federal Agenda Amid D.C. Policy Shifts, ‘Big Beautiful Bill’ Impacts

ARTICLE SUMMARY: The Will County Board's Legislative Committee is reshaping its federal priorities for 2026, adding new language on environmental justice and LGBTQIA+ rights while creating a more transparent process for...
WCO-Public-Safety.3

Health Department Seeks $1 Million Levy Increase to Prevent “Weakened System”

Article Summary: The Will County Health Department is asking for a $1 million increase to its property tax levy to save 11 critical jobs that are at risk as post-pandemic...
WCO-Cap-Imp-8.5.3

County Rolls Out New “OneMeeting” Software to Improve Public Access

ARTICLE SUMMARY: Will County has officially launched a new agenda and meeting management software called "OneMeeting," aimed at improving transparency and making it easier for the public and officials to access...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for August 5, 2025

The Will County Board’s Finance Committee confronted major budget challenges during its Tuesday meeting, led by a stark presentation from the Will County Health Department. Health officials are requesting an...
WCO-PZ-8.12.2

Will County PZC Approves Rezoning for Truck Repair Facility on Manhattan Road Amid Resident Concerns

Article Summary: The Will County Planning and Zoning Commission voted 4-2 to rezone nearly 14 acres in Joliet Township for a truck repair facility. The approval came after a neighboring...
WCO-PZ-Aug-5.3

Key Stretch of Bell Road on Track for Thanksgiving Reopening, Committee Approves Additional Funds

ARTICLE SUMMARY Construction on Bell Road between 159th and 151st Streets is scheduled to have all lanes open by Thanksgiving, officials announced as the Public Works & Transportation Committee approved a...
WCO-LEG-8.5.2

Will County Leglislative Committee Opposes Federal Push for Heavier, Longer Trucks

ARTICLE SUMMARY: The Will County Board's Legislative Committee unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on national roadways. Will...
WCO-Public-Safety.2

Will County Reports Progress in Opioid Fight, Highlights New FDA Labeling Rules

Article Summary: Will County is seeing a reduction in opioid overdose deaths and is expanding access to the reversal drug Narcan, health officials reported. The department also drew attention to...
WCO-Cap-Imp-8.5.4

In-House Staff Completes Major Renovations at Will County Adult Detention Facility

ARTICLE SUMMARY: Maintenance staff at the Will County Adult Detention Facility recently completed extensive renovations in-house, including a new control center and the full restoration of a 48-cell housing unit, saving...
Land-use-8.5.25

Will County Advances Truck Repair Facility Plan on Manhattan Road Despite Resident Objections

Article Summary: A proposal to rezone nearly 14 acres on Manhattan Road for a truck repair facility advanced after receiving a recommendation for approval from the Will County Land Use...
WCO-PZ-8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO-PZ-Aug-5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...