Will County Board Graphic.02

Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus

Spread the love

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026

Article Summary
The Will County Capital Improvements & IT Committee is evaluating four multi-million-dollar proposals to replace aging county buildings, balancing the specific spatial needs of the County Clerk’s office with a debate over the legalities and logistics of potentially relocating the county seat.

Will County Master Plan Key Points:

  • Wight & Company presented four building consolidation options ranging in cost from $239 million to over $306 million.

  • County Clerk Kimberly Fladhammer and her staff requested 20,000 to 40,000 square feet of dedicated warehouse space for election equipment, which is not fully addressed in current proposals.

  • Board Member Steve Balich (R-Homer Glen) suggested moving county operations to a “green space” campus outside Joliet to solve parking and expansion issues.

  • The State’s Attorney’s office confirmed that moving the county seat from Joliet requires a county-wide voter referendum.

The Will County Board Capital Improvements & IT Committee on Tuesday, May 5, 2026, reviewed four extensive architectural proposals from Wight & Company to consolidate and replace aging county facilities, sparking a complex debate over space, cost, and location.

With the current County Office Building and the EMCO building requiring significant ongoing maintenance, the county is exploring a massive infrastructure overhaul. Mike Mahoney from the County Executive’s office presented the four options, which all hover around the $300 million mark.

Option 1 proposes two separate county buildings—one for auxiliary court functions (State’s Attorney and Public Defender) with a parking garage, and a new County Office Building at the site of the old courthouse. The estimated cost ranges from $239,030,000 to $302,030,000.

Option 2 features a partnership with the City of Joliet, combining city and county offices into one complex, with an estimated total cost between $239,550,000 and $303,730,000, though Joliet would cover the costs of its own square footage. Options 3 and 4 present variations of these configurations, with Option 4 encompassing a massive 385,600 gross square-foot building housing Judicial Agency Offices, the County Office, and the City of Joliet, plus a 230,400 square-foot parking garage, topping out at an estimated $306,040,000.

“Both buildings that we’re in right now for the State’s Attorney and probation… and the EMCO building, that building is in, I don’t want to say a state of disrepair, but it is very old,” Mahoney told the committee. “There are wood floors still throughout, wood subflooring throughout. It needs a lot of work to keep maintaining, and it will continue to cost the county additional millions of dollars in maintenance costs over the next five to 10 years. Obviously, the same with this building [the current County Office Building].”

The logistical challenge of the master plan was highlighted by the Will County Clerk’s Office. County Clerk Kimberly Fladhammer and her Chief of Staff addressed the committee regarding critical space shortages affecting election operations.

The Clerk’s office currently operates with approximately 4,000 square feet in the basement to house election day equipment and cages. They noted that comparable counties utilize warehouses ranging from 20,000 to 40,000 square feet. Furthermore, the office requires dedicated space for election judge training—currently held in a borrowed Human Resources conference room—and a secure event space for central and provisional ballot counting.

“The proposal by White was approximately 33,000 square feet for the county clerk’s office, which I think would be sufficient for the day-to-day operational issues with vital records,” the Clerk’s Chief of Staff said. However, she noted it would not satisfy the massive warehouse need for equipment, which requires specialized logistical access like freight elevators and loading docks.

Board Member Steve Balich (R-Homer Glen) argued that the spatial constraints and parking issues in downtown Joliet justify moving the county’s operations entirely.

“Most of the people on the board back in the day before the courthouse was built wanted to create a green space and build our own campus, and that would eliminate all the problems going forward,” Balich said. “There’s a whole lot of land in Joliet when you go west close to Grundy County like by Minooka… There’s a whole lot of land where they want to put big solar farms in Manhattan.”

However, relocating the core functions of the county government faces a strict legal hurdle. An Assistant State’s Attorney present at the meeting clarified the statutory limitations.

“The county seat is Joliet,” the attorney stated. “You need a referendum of the whole county to move the county seat. You could move it if everybody agreed in the county that voted for it… but we cannot move the county seat just by county board action.”

Board Member Jacqueline Traynere (D-Bolingbrook), attending the meeting as a guest, reminded the committee of the historical context behind keeping the campus downtown.

“The cost to move people that are housed in the jail to a courthouse that would be built on a green space in New Lenox was just not going to be supported,” Traynere said. “Not only the cost, but just the security issues. So that was the main reason why we chose to go forward with the courthouse downtown as opposed to a green space.”

The committee did not take a formal vote on the options. Instead, members requested that Wight & Company provide additional configurations, including assessing the feasibility of adding floors to the current County Office Building—a 1949 structure originally built as a Sears store—and exploring development on the north end of the current parking lot.

Leave a Comment





Latest News Stories

Green Garden Township Supervisor Dean Christofilos address the Will County Planning & Zoning Commission meeting on March 30. Photo by Andrea Arens.

Will County P&Z Recommends Denial of 6,000-Acre “Pride of the Prairie” Solar Project After Contentious Hearing

By Andrea Arens JOLIET — After more than eight hours of testimony and public comment spanning two nights, the Will County Planning and Zoning Commission voted 4–2 to recommend denial...
U.S., NATO alliance on the line as Trump set to meet with Rutte

U.S., NATO alliance on the line as Trump set to meet with Rutte

By Sarah Roderick-FitchThe Center Square Tensions are running high between President Donald Trump and NATO leaders, as grumblings grow over the U.S. withdrawing from the alliance. NATO’s relationship with the...
BREAKING: Trump fires Bondi, Blanche to lead DOJ

BREAKING: Trump fires Bondi, Blanche to lead DOJ

By Andrew RiceThe Center Square President Donald Trump removed Attorney General Pam Bondi from the Department of Justice on Thursday, according to a post on social media. "Pam Bondi is...
States sue Trump administration over rollback of some air pollution regulations

States sue Trump administration over rollback of some air pollution regulations

By Elyse ApelThe Center Square Minnesota Attorney General Keith Ellison is co-leading a multi-state lawsuit challenging the Trump administration’s rollback of some federal limits on toxic air pollution. The lawsuit...
Energy affordability report ranks Illinois 31st, warns of 'burdensome' mandates

Energy affordability report ranks Illinois 31st, warns of ‘burdensome’ mandates

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – According to a new report on energy affordability, burdensome mandates are making Illinois more expensive. The American...
Illinois voices weigh in on birthright citizenship case

Illinois voices weigh in on birthright citizenship case

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – As the U.S. Supreme Court considers a high-stakes challenge to birthright citizenship, a constitutional law expert...
U.S. rep.: Mexico still not delivering water to South Texas, despite claims

U.S. rep.: Mexico still not delivering water to South Texas, despite claims

By Bethany BlankleyThe Center Square Despite repeated claims by Trump administration officials, Mexico is not delivering water as promised to South Texas in accordance with a long-standing treaty. In January,...
Supporters say will storage option would streamline judicial process

Supporters say will storage option would streamline judicial process

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Supporters say an Illinois House bill allowing county clerks to develop a will depository would streamline judicial...
Dallas Fed: Geopolitical conflicts creating uncertainty for U.S. oil and gas industry

Dallas Fed: Geopolitical conflicts creating uncertainty for U.S. oil and gas industry

By Bethany BlankleyThe Center Square A new quarterly Dallas Fed Energy Survey indicates the U.S.-Israeli conflict with Iran and other geopolitical conflicts are negatively impacting and creating uncertainty for the...
Illinois Quick Hits: Pritzker pushes for E15

Illinois Quick Hits: Pritzker pushes for E15

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Gov. J.B. Pritzker is asking leaders of the U.S. House on Environment and Public Works Committee...
Lincoln Way West Warriors Softball

Lincoln-Way West Blanks Rival Lincoln-Way Central 10-0 in WJOL Tournament

The Lincoln-Way West varsity softball team continued its dominant spring on Wednesday evening, rolling to a 10-0 shutout victory over cross-town rival Lincoln-Way Central. Competing in the WJOL Tournament, the...
Lincoln Way West Warriors Baseball

Southside (AL) Outlasts Lincoln-Way West 6-4 Despite Howard’s Power Surge

A monster offensive performance by Jacob Howard wasn't enough to propel the Lincoln-Way West varsity baseball team to victory, as they fell 6-4 to Southside in a hard-fought neutral-site contest....
Board Book

Manhattan School District Adopts BoardBook Premier to Digitize Meetings and Enhance Public Transparency

Manhattan School District 114 Meeting | March 25, 2026 Article Summary: To modernize operations and improve public access to information, the Manhattan School District 114 Board of Education completed a live...
Screenshot 2026-03-29 at 4.44.29 PM

Local Farmer Pitches Farmland Preservation Program to Combat Will County Industrialization

Village of Manhattan Meeting | March 16, 2026 Article Summary: A local farmer and Will County Planning and Zoning Commissioner urged the Manhattan Village Board to support a new farmland preservation...
Trump addresses nation on Iran strikes; signals conflict nearing end

Trump addresses nation on Iran strikes; signals conflict nearing end

By Sarah Roderick-FitchThe Center Square Just over a month after Operation Epic Fury began, President Donald Trump Wednesday proclaimed U.S. strikes on Iran are nearing completion, while telling allies to...