Will County Executive Committee Backs Funding Pursuit for $2.33 Million Harris Drive Property Buyouts

Spread the love

Will County Board Executive Committee Meeting | May 14, 2026

Article Summary: The Will County Board Executive Committee on Thursday, May 14, 2026, agreed to pursue state and federal grant funding for a recommended property-buyout plan to address chronic flooding and septic backups along Harris Drive in unincorporated Plainfield Township, where Baxter & Woodman engineers concluded that acquiring up to nine homes for an estimated $2.33 million is the only modeled alternative that fully mitigates flooding at the most affected properties.

Harris Drive Stormwater Study Key Points:

  • Baxter & Woodman’s study identified four alternatives ranging from a $1.7 million 30-inch storm sewer to a $3.28 million 48-inch storm sewer routed under Interstate 55 to the DuPage River, alongside the recommended $2.33 million targeted property buyout option.
  • The county’s Stormwater Management Planning Committee has an annual budget of only $300,000, prompting the executive committee to seek outside grant funding through the Illinois Department of Natural Resources, FEMA and the Illinois Environmental Protection Agency.
  • Grant application deadlines for FEMA’s Flood Mitigation Assistance program and Building Resilient Infrastructure and Communities program fall on June 26 and July 1, according to the Land Use Department.
  • All nine impacted homeowners have indicated willingness to participate in a buyout, county officials said.

WILL COUNTY — The Will County Board Executive Committee on Thursday, May 14, 2026, voted to pursue state and federal grant funding to acquire nine flood-prone homes along Harris Drive in unincorporated Plainfield Township, where residents have endured frequent flooding and septic system backups that have at times rendered the houses uninhabitable. The motion, made by Dawn Bullock and seconded by Sherry Newquist, passed on a voice vote.

The action follows a Will County Stormwater Management Planning Committee study completed by Baxter & Woodman, Inc. that evaluated four engineering alternatives for the neighborhood located between the I-55 Northeast Frontage Road and Addleman Street. According to the study, multiple homes on both the north and south sides of Harris Drive flood after stormwater flows north from agricultural fields and then drains through a swale to retention basins in the adjoining Squire’s Mill subdivision. The segment is not connected to the City of Joliet’s water and sewer system, and many residents experience septic backups linked to high groundwater levels.

The engineers concluded that targeted property buyouts — designated as Alternative 4 — are the only option that completely mitigates flooding at the acquired homes. Acquiring nine properties at an average Will County tax assessor value of $259,000 each would cost up to $2.33 million. Smaller buyout configurations would cost roughly $1.59 million for six homes or $2.05 million for eight homes, the report states.

Sarah Coleman, chief subdivision engineer in the Land Use Department, told the committee that Alternative 4 was selected because the alternative engineered solutions either provided insufficient protection or proved prohibitively expensive. The first two alternatives — a $1.7 million 30-inch storm sewer in the Harris Drive right-of-way and a $2.86 million plan combining home buyouts with detention basins — are constrained by the downstream capacity of the Squire’s Mill retention basins, the study found. A $3.28 million third alternative would jack and bore a 48-inch storm sewer under I-55 to discharge directly to the DuPage River, but its effectiveness during major storms is limited by river stages at flood elevations.

The Funding Question

Daniel J. Butler, who represents District 3 alongside Newquist and chairs the Public Health and Safety Committee, told members the stormwater committee lacks the budget to fund the project on its own and has concluded the matter must come before the full board for additional funding consideration. “They got nine homes. They cannot use their bathrooms. They all have septic fields and none of them work,” Butler said.

Coleman said the county is preparing to apply for flood mitigation assistance through both the Illinois Department of Natural Resources, which operates a rolling acquisition-and-demolition program offering reimbursable funding of up to $1 million per community, and through FEMA’s Flood Mitigation Assistance and Hazard Mitigation Grant programs, which typically reimburse 75 percent of federal costs with a 25 percent local match. Deadlines for the BRIC and FMA programs are June 26 and July 1, respectively.

Newquist, who chairs the Finance Committee and represents District 3, said she shared the concern about the long process to acquire the homes — the IDNR pathway runs two to three years, FEMA programs run three to six years, and a similar Army Corps of Engineers project on the DuPage River is in its ninth year and still acquiring property — but said all nine Harris Drive homeowners are aware of the timeline and prefer the buyout. “What we’re looking for is just to say we’re going to apply for these grants, a series of grants, not just one or two, but a bunch of them so that we can come up with the money to mitigate the issue,” Newquist said.

Dissent Over Removing Homes From the Market

Jackie Traynere, who chairs the Public Works and Transportation Committee, expressed concern about removing homes from the available housing inventory. “We have a shortage of housing now,” Traynere said, suggesting one of the engineered alternatives might better serve the public over time. Oxley asked whether a detention pond on five acres of the upstream farmland could redirect runoff away from the homes; Coleman said a similar concept was studied in 2011 and came in at more than $3 million before property acquisition costs and would not have addressed flooding on the north side of Harris Drive.

The Baxter & Woodman study also identified the IEPA’s Water Pollution Control Loan Program and Section 319(h) Nonpoint Source Grants as possible funding routes if engineered ditch work and detention become the preferred path. The firm recommended that the county pursue Alternative 3 or Alternative 4 contingent on funding availability, and noted that even under Alternative 4, the installation of backflow preventers at the Squire’s Mill detention basin outfalls — at a cost of $30,000 to $50,000 — should still be considered.

The stormwater issue has been before the county for more than two decades, but Will County Board Speaker Joe VanDuyne noted the executive committee has only been formally engaged in the discussion in the past several months. The board’s next regular meeting is May 21, 2026.

Leave a Comment





Latest News Stories

lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
District 114 Graphic

Manhattan School District 114 Approves $41.5 Million Budget for FY26

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a fiscal year 2026 budget with $41.5 million in expenditures, a figure significantly influenced by the final costs...
Peotone fire district graphic logo.1

Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings

Article Summary: The Manhattan Fire Protection District is moving forward with plans for a new Station 81 after holding a public hearing for an $8.75 million bond sale and approving...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...