Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Medicaid-logo

Federal Reconciliation Bill Targets Medicaid, SNAP Programs

Will County Legislators Briefed on Potential Local Impacts Federal legislation making sweeping cuts to Medicaid and food assistance programs could significantly impact Will County residents and services, county legislators learned...
MH VB 6-3

Manhattan Celebrates 100-Year Resident Ruth Munt at Village Board Meeting

Manhattan resident Ruth Munt received a special 100th birthday celebration at Tuesday's Village Board meeting, sharing her remarkable perspective on seven decades of community growth. Munt, who moved to Manhattan...
will-county-board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...
will-county-board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
MH VB 6-3

Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan's Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final...
will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
MH VB 6-3

Village Releases $2.8 Million Letter of Credit for Completed Stonegate Subdivision

The Manhattan Village Board approved the release of a nearly $2.9 million letter of credit for the Stonegate subdivision after village engineers confirmed all required public improvements have been completed....
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...