Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Manhattan Township

Manhattan Township Recommends Denial of Bruns Road Rodeo Permit Amid Neighbor Objections

The Manhattan Township Board unanimously recommended that Will County deny a permit for a large-scale commercial rodeo on Bruns Road, following a contentious public hearing where neighbors cited a history...
Manhattan Township

Road Contract Awarded as Township Races Against Bridge Funding Deadline

The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a...
Manhattan Township

Manhattan Township Halts Electric Aggregation Program, Citing Poor Pricing

Residents in unincorporated Manhattan Township will no longer be enrolled in a group electricity purchasing plan after the Township Board voted unanimously not to renew its electric aggregation contract. The...
Manhattan Township

Meeting Briefs: Manhattan Township for April 8, 2025

Assessor’s Office to Replace Server, Receives New Tax Multiplier: Assessor Joe Oldani reported that the township’s server is not compliant with current security methods and must be replaced by the end...
MFPD-Logo-Fire District

Fire District Receives Clean Audit, Adds 9 New Firefighters Despite Staff Departures

The Manhattan Fire Protection District received a clean audit report for fiscal year 2023 while addressing staffing challenges with nine new part-time firefighters set to join the department at the...
MFPD-Logo-Fire District

Construction Manager Decision Delayed for New Fire Station Project

The Manhattan Fire Protection District has postponed a decision on hiring a construction management company for its new fire station project while fee structures are finalized. Board members met with...
MFPD-Logo-Fire District

Manhattan Fire District March 17 Meeting Briefs

Vehicle Updates Progressing: The new Tahoe ordered last year has arrived but will require several months before entering service. The ambulance damaged in December's crash is currently at the body...
Manhattan Township

Manhattan Township to Fight State Consolidation Bills, Citing Threat to Local Services

The Manhattan Township Board is mounting a formal opposition to a series of state bills that officials believe threaten the existence of township governments across Illinois. During their monthly meeting...
Manhattan Township

Massive Battery Storage Facility Proposed in Manhattan Township, Could Be “Largest in Illinois”

A proposal for a 15-acre battery storage facility that could be the "largest substation in Illinois" is under consideration in Manhattan Township, a project that could reshape a portion of...
Manhattan Township

Proposed Bruns Road Rodeo Sparks Concerns Over Safety, Zoning, and Past Violations

A proposal to host a large, multi-weekend rodeo on Bruns Road has raised numerous red flags for the Manhattan Township Board, which cited concerns ranging from public safety and zoning...
Manhattan Township

Soltage Solar Farm Clears County Committee; Township Eyes Aesthetic Improvements

The proposed Soltage Solar Farm has passed a key hurdle, gaining approval from the Will County Land Use Committee in a 5-1 vote, Manhattan Township Supervisor James 'Jim' Walsh reported...
Meeting Briefs

Meeting Briefs: Manhattan Township for March 11, 2025

Dial-A-Ride Service to be Absorbed by County: The Southwest Dial-A-Ride service is being absorbed by the larger Will County Dial-A-Ride service, which is offered through PACE. Township officials expressed hope that...
Blue flasher light of siren of police car

Manhattan Police Reports

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On March 5, officers stopped Leal Acosta, Julio C (25)...
MFPD-Logo-Fire District

Manhattan Fire District Advances New Station Construction, Approves $210,000 Ambulance Replacement

The Manhattan Fire Protection District is moving closer to breaking ground on its new fire station, with construction documents expected to be complete next month and a potential groundbreaking scheduled...
MFPD-Logo-Fire District

Former Peotone Firefighter Mike Shivers Recommended for Fire District Board Position

The Manhattan Fire Protection District board unanimously recommended Mike Shivers to fill a vacant trustee position left by the recent death of Trustee Bill Osborne. Shivers, a former Peotone Fire...