Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a project with a preliminary total cost estimated at up to $750,000.

During a July 28 workshop meeting, the board reviewed building designs, debated hiring a project manager, and discussed a tight construction timeline to meet a crucial grant deadline. The plan also drew pointed questions from residents about the project’s budget, placement, and potential impact on neighbors.

The project hinges on securing the transfer of a $500,000 grant from Will County, originally approved for renovating the current town hall. Supervisor Dean Christofilos reported that the application to repurpose the funds for a new build has been submitted to the county’s consultant, Assensure, and is expected to be forwarded to the county for a decision within weeks. A key condition for the grant is a strict project completion deadline of December 31, 2026.

“Time is of the essence,” Christofilos said, outlining an aggressive timeline that includes a special electorate meeting on September 8 for residents to vote on approving the new construction.

The board reviewed several post-frame building options from Lester Buildings. The most discussed design was a roughly 4,000-square-foot structure featuring stone wainscoting and prominent windows, with an estimated cost of around $250,000 for the building shell alone. With concrete work estimated at $40,000 and interior finishing potentially costing $200,000 or more, plus expenses for septic, utilities, and a parking lot, the total project cost is projected to be around $750,000.

A significant portion of the discussion focused on how to manage the complex project. While initially considering dividing responsibilities among board members, the trustees appeared to lean toward hiring a professional general contractor or project manager to ensure the development stays on schedule.

“Somebody get some people out of the township… to see what we can do,” said Trustee Monroe Striggow. “I think we got more than enough to do besides trying to build ourselves.”

The plan drew sharp criticism from some residents in attendance. One resident, Mike, who identified himself as an HVAC professional, warned that the budget may not account for significant expenses like storm sewers, landscaping, or a potentially required sprinkler system for a public assembly building.

“Your expenses that I saw not accounted for, you could easily be up to the 150 mark that’s still not in that budget,” he cautioned. He also questioned the community’s appetite for the expense, stating, “They don’t want to spend that kind of money. They want to take the free money and that’s it.”

Another key concern came from a neighboring resident, who identified himself as Chadman L., whose property abuts the proposed site. He expressed serious reservations about the building’s placement.

“My wife’s hands in that backyard. My son plays in the backyard. I’m going to have people sitting here… windows staring at my family,” he said, also noting concerns about traffic, noise, and parking lot lights.

Supervisor Christofilos defended the project’s vision, framing it as a long-term investment in the community.

“We have to see the vision for the community,” Christofilos stated. “We could have veterans things. We could have bingo. We could have seniors events. You could have a lot of different things to bring the community together.”

The board plans to continue refining the building design and seeking a project manager while awaiting a decision from Will County on the grant transfer. If the grant is approved, the project’s fate will ultimately be decided by residents at the September 8 electorate meeting.

Leave a Comment





Latest News Stories

Screenshot 2025-06-05 at 1.43.56 PM

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...
Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
Police blue and red flashing light on the car in the street

Manhattan Police Reports

On May 14th, at 1225 A.M. officers observed a vehicle traveling in the area of West North & Foxford at a high rate of speed. Officers radar indicated the gray...
Manhattan School District 114 Logo Graphic

Manhattan District Adopts New Math Program After Comprehensive Review

The Manhattan School District 114 Board of Education unanimously approved the adoption of Eureka Math Squared for kindergarten through eighth grade on Tuesday, concluding a year-long evaluation process involving 25...
Manhattan School District 114 Logo Graphic

Manhattan Junior High Scholastic Bowl Team Places Second at State Championship

Manhattan Junior High School's scholastic bowl team achieved a historic milestone by placing second in the state championship, marking the first time in the program's eight-year history that the team...
Manhattan School District 114 Logo Graphic

Enrollment Growth Prompts Staffing Discussions as Construction Continues

Manhattan School District 114 continues managing significant enrollment growth while construction projects remain on schedule for completion by the end of the school year. Current kindergarten enrollment of 218 students...
Manhattan School District 114 Logo Graphic

School District 114 Meeting Briefs

Budget Display Scheduled: The district's fiscal year 2025 amended budget will be on public display from May 15 through June 17, with board approval scheduled for the June 17 meeting....
Manhattan Township

Manhattan Road District Eyes $2.1M Budget, Hinges on Unguaranteed Solar Farm Funds

The Manhattan Township Road District is proposing a $2.15 million budget for the upcoming fiscal year, a plan that includes the purchase of a new truck and finishing a storage...
Manhattan Township

Manhattan Township Delays Decision on Critical Server Upgrade Amid Security Concerns

Manhattan Township officials are weighing a costly but necessary technology upgrade after learning their primary server is a decade old and runs on unsupported software, posing a potential cybersecurity risk....
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
Manhattan Township

Assessor Announces End to “Empathetic” Tax Reductions, Raises Senior Freeze Threshold

Manhattan Township homeowners will see two significant changes in property assessment rules, including the end of a long-standing practice of granting tax reductions for fire-damaged properties and a beneficial increase...
Manhattan Township

Meeting Briefs: Manhattan Township for May 13, 2025

Officials Sworn into Office: Clerk Kelly Baltas administered the oath of office to newly elected and re-elected officials. Taking the oath were Supervisor James F. Walsh and Trustees Eileen Fitzer, Paul...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
Village of Manhattan Logo Graphic

Manhattan Swears In New Officials, Tables Fire Code Discussion

Village postpones St. Joseph's school sprinkler decision as benefactors emerge to help with costs Mayor Mike Adrieansen began his second term alongside newly elected Village Clerk Rebecca Bouck and trustees...