Kankakee Bridge Project Out for Bid at $1.6 Million, Baker Road Bridge Nears Completion
Manhattan Township Meeting | July 2025
Article Summary: Manhattan Township is moving forward with two significant infrastructure projects, with the Kankakee Bridge reconstruction now out for bid at an estimated cost of $1.6 million. Meanwhile, the Baker Road Bridge reconstruction project is more than halfway complete, according to a report from the Highway Commissioner.
Township Bridge Projects Key Points:
-
The Kankakee Bridge reconstruction project is now accepting bids, with the bid opening scheduled for July 16.
-
The estimated cost for the Kankakee Bridge project is $1.6 million.
-
Work on the Baker Road Bridge reconstruction is currently 55% complete.
Manhattan Township is advancing two major bridge reconstruction projects, with one heading to bid for $1.6 million and another already past the halfway point of construction, the township board learned on Tuesday, July 8, 2025.
In his monthly report, Highway Commissioner Jim Baltas announced that the Kankakee Bridge reconstruction project is now officially out for bid. The bid opening is scheduled for July 16, with the project carrying an estimated price tag of $1.6 million. This marks a critical step in moving the long-planned infrastructure upgrade toward the construction phase.
Baltas also provided a positive update on the Baker Road Bridge project, reporting that the reconstruction is now 55% complete. The project has been underway for several months and is progressing on schedule, aiming to restore a key local transportation link for residents. Both projects represent a significant investment in maintaining and improving the township’s rural road and bridge network.
Latest News Stories
Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property
Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Sheepdog Firearms Gets Green Light for Special Use Permit in Monee
New Lenox Prepares for Grand Opening of Wintrust Crossroads Sports Complex
New Lenox D122 Board Approves Tentative Budget, Sets September Public Hearing
New Lenox Township Food Pantry Reports Record Demand in May
New Lenox to Dedicate Street Honoring Pope Leo XIV, Citing Deep Local Ties
D122 Renews Insurance Policies for Nearly $490,000
New Lenox Township Addresses Cemetery Needs, Appoints New Liaison
New Lenox Police Chief Louis Alessandrini Retires; Sgt. David Nykiel Promoted in Leadership Transition
Monee to Receive $250,000 Donation in Solar Project Agreement
New Lenox Park District Board Approves 2025-2026 Budget